Free job shop production schedule template (Excel)

Yes. This free Excel template plans a job shop by machine: list each job's operations in routing order with their hours and a planned day, and it flags any operation planned after the job's due date or before its previous operation, and shows the hours booked on each machine each day in red when they exceed that machine's shift. It suits up to a few dozen open jobs and one planner; past that, use scheduling software.

Pujan Motiwala · Written for US job shops and small manufacturers · QuickBooks facts checked against Intuit's pages on

A spreadsheet grid on a clipboard with coloured bars like booked machine time, a steel ruler and a pencil across it: a schedule template.

Is there a free production schedule template for a job shop?

Yes, this one: Job shop schedule template (Excel), free under CC BY 4.0. It opens in Excel or Google Sheets and needs no macros.

It is filled in with the six made-up jobs from the schedule demo, so you can see it working before you replace them with your own.

What's in the template?

Three sheets: machines, jobs and the daily load.

SheetWhat you enterWhat it works out
MachinesEach machine or work center and its hours per day (8 for one shift, 16 for two)Nothing; the other sheets read it
JobsOne row per operation, in routing order: job, due date, operation number, machine, hours, planned dayA check on every row: OK, "After due date", or "Before previous operation"
LoadThe first day of the planHours booked per machine for each of the next 20 working days, red where a machine is over its hours

The machine column is a drop-down from the Machines sheet, so a typo can't create a machine that doesn't exist.

How do you fill it in?

Machines first, then each job's operations, then a planned day for each:

  1. List your machines and their shift hours.
  2. Enter each open job's operations from its routing, with the quoted hours. If your quotes are built from operations and times, copy them; that's also what job costing compares against.
  3. Give each operation a planned day, earliest due date first, and each operation no earlier than the one before it.
  4. Look at the Load sheet. Red means that machine has more hours booked than it has that day: move an operation, split it across days, or add a shift.
  5. Fix every "After due date" either by moving work or by telling the customer now, not on the due date.

The sample shows the point of step 4. Three days come up red, and the welding cell on Wednesday is the real problem: 13 hours booked on an 8-hour day, which is why frame job J-103 runs late in the demo. The other two (the laser on Monday, the press brake on Tuesday, 9 hours each) are operations that run over into the next day, which the template counts on the day they start.

How much can your machines take in a week?

Machines × shifts × hours × days. Three machines on two 8-hour shifts, five days a week, give 3 × 2 × 8 × 5 = 240 hours a week, and 80 hours for each machine. The Load sheet does the same sum per machine per day: the sample's welding cell on Wednesday, 13 hours booked on an 8-hour day, is 162.5% of its capacity, so it shows red.

When does a spreadsheet schedule stop being enough?

When more than one person plans, or when you need the later operations to move by themselves. Owners on Practical Machinist describe starting with a whiteboard, moving to an Excel grid of machines by day, and finding it works while one person owns it. A spreadsheet schedule is honest about what it is:

  • One planner. Two people editing copies of it will drift apart; owners on forums say this is where spreadsheets break.
  • Nothing moves by itself. When an operation slips, you move the later ones by hand. Scheduling software moves the whole chain (finite capacity).
  • It doesn't know what's finished. Progress has to be typed in; without it the plan drifts from the floor. That's what WIP tracking fixes.
  • Hours land on one day. An operation's hours all count on its planned day, so long operations show as an overload; split them into one row per day if that matters.

When those limits cost you late jobs every week, read what production scheduling software does and try the demo with your own jobs.

Quotes, jobs, routings, stock and shop-floor time in one system, with QuickBooks kept for the books. Start with a working prototype of your main workflow, on your own data, in 2 weeks for $1,500, credited to the build if you continue.

Stock, reservations and approvals in a live system, with sample logins: try the inventory demo.

Official sources

What this page is not

A guide written by Ahrom Labs, a software company that builds operations systems for manufacturers. Where it describes QuickBooks, the facts come from Intuit's own pages on the date shown, and Intuit changes its plans often: check your edition before relying on it. QuickBooks is a trademark of Intuit Inc.; Ahrom Labs is not affiliated with Intuit. Not accounting or tax advice. Last updated .