IBR 2026 for boiler manufacturers
What a boiler maker files under the Indian Boiler Regulations, 2026, which replaced IBR 1950 on 1 October 2026: the renumbered forms, the documents for registration, how long records are kept, and the rules for small industrial boilers. Each page quotes the Gazette and links the official text.
Pujan Motiwala · Checked against the Gazette on · IBR 2026, in force from 1 October 2026
Guides
- What changed with the Boilers Act 2025 and IBR 2026
The Indian Boiler Regulations, 2026 replaced the Indian Boiler Regulations, 1950 on 1 October 2026, under the Boilers Act, 2025. The folder's forms were renumbered — the maker's Form III is now Form IV Part A — certificates can be filed electronically with digital signatures, and manufacturers must keep boiler records for at least five years.
- Documents for boiler registration under IBR 2026
Under regulation 8 of IBR 2026, a boiler's registration application goes to the Chief Inspector with four sets of documents: the Inspecting Authority's certificate (Form I Part B or C), the maker's certificate (Form IV Part A), drawings, and the material certificates (Form V Part A, with the Form V Part B extract).
- How long boiler records must be kept under IBR 2026
Regulation 308 of IBR 2026 sets three retention periods for a boiler's certificates and approved drawings: the Inspecting Authority keeps them at least 3 years after registration, the manufacturer at least 5 years, and the owner for the boiler's entire life, passing them to any new owner.
- Small industrial boilers under IBR 2026
Under IBR 2026 a small industrial boiler is a shell boiler up to 7 kg/cm² (g) holding more than 25 and up to 500 litres, or a coil, once-through or water tube boiler up to 12 kg/cm² (g) and 150 litres. Its certificate of manufacture and test is Form XXII, which was Form XVII under IBR 1950.
- IBR 2026 forms list, and their IBR 1950 names
Every form from Form I to Form XXIII, the regulation it falls under, and the IBR 1950 form it replaced.
The forms in a boiler's folder
- Form I Part BCertificate of inspection for shop assembled boilers · was Form II(1)
- Form I Part CCertificate of inspection for site assembled boilers at maker's works · was Form II(2)
- Form I Part DInspecting Authority's certificate of inspection during construction of boilers with permitted variations from standard conditions · was Form II-B
- Form I Part EInspecting Authority's certificate of inspection after completion of boiler erection at assembly site · was Form II-C
- Form IV Part AConstructor's certificate of manufacture and test · was Form III
- Form IV Part BCertificate of manufacture and test for pipes · was Form III-A
- Form IV Part CCertificate of manufacture and test for tubes · was Form III-B
- Form V Part ASteel maker's certificate of manufacture and results of tests · was Form IV
- Form V Part BCertificate of manufacture and results of tests in lieu of original test certificates · was Form IV-A
- Form XProvisional order under section 14 of the Boilers Act, 2025 · was Form V
- Form XIMemorandum of Inspection Book or Registration Book · was Form I
- Form XIICertificate for use of a boiler · was Form VI
- Form XXIICertificate of manufacture and test for small industrial boilers · was Form XVII
See a boiler's IBR folder produced from its material certificates, with a sample company.
Built for a boiler manufacturer: ERP for boiler manufacturers · how the folder is produced
Official sources
- Indian Boiler Regulations, 2026 (Gazette of India, Extraordinary, No. 596). Central Boilers Board, Department for Promotion of Industry and Internal Trade, October 1, 2026.
What this page is not
A guide written by Ahrom Labs from the Gazette text; not legal advice. The Gazette governs wherever this page differs from it, and a state's Chief Inspector of Boilers may set procedures of their own. Last updated .