Hold point

A step on an inspection and test plan that work may not pass until a named party (shop QC, the Authorized Inspector or the customer's inspector) has inspected it and released it. A witness point needs only notice; a hold point stops the job.

Pujan Motiwala ·

Hold points are written on the job's inspection and test plan beside witness (W), review (R) and surveillance (S) points; ASME doesn't define the letters, the purchase order or the shop's procedure does. Typical holds are material receipt, fit-up before welding, NDE before a joint is covered, and the hydrostatic test. A hold only works if the next step is actually refused until it is released, and stays refused while a nonconformance report is open.

Talk to us about your systems.

Tell us what's held together with workarounds right now. We reply to every message ourselves.