Inspection and test plan (ITP) for pressure vessels

An inspection and test plan (ITP) lists every inspection and test on a job in the order the work happens, with the document each is checked against, the acceptance criteria, the record it produces, and who must review, witness or release it: the shop's QC, the Authorized Inspector and the customer. Hold points stop the work until the named party signs; witness points need notice; review points are document checks.

Pujan Motiwala · Written to the ASME BPVC 2025 Edition · checked against ASME's and the National Board's public pages on

A clipboard with a blank checklist and a red hold tag tied to the clip: a job's inspection and test plan with its hold points.
Video chapters (10)
  1. 0:00What an ASME Inspection & Test Plan (ITP) Does (Appendix 10 & UG-90)
  2. 0:224 ITP Gate Codes (H, W, R, S) & Prerequisite Blocking
  3. 0:44The 10 ITP Columns Explained (Worked Step 4.2 — Weld L1 RT)
  4. 1:053 Parties Setting Holds & 3 Reasons Paper ITPs Skip Gates
  5. 1:28Shell-and-Tube Heat Exchanger ITP Stages & AI Sign-Offs
  6. 1:48Failed RT Recovery, NCR Loop & Free CC BY 4.0 Excel/Word/PDF Templates
  7. 2:06Official Citations: BPV-GUI-03 Section 3, Appendix 10, UG-90 & UW-51
  8. 2:26Enforcing 60-Point Exchanger ITP Prerequisites (Job AB-1005) in ERP
  9. 2:482025 Edition Notice & Authorized Inspector Verification
  10. 3:00Next Steps: Nonconformance Reports (S40), QC Manual (S20) & Exchangers (S33)

What is an inspection and test plan?

An inspection and test plan (ITP, sometimes a quality plan or inspection traveler) is the job's list of every inspection and test, in fabrication order, with who checks each one and what proves it was done. It turns the quality control manual's general promises into one job's steps: this shell, these welds, this hydro test.

The ASME Code doesn't use the term "ITP". What it does require is an examination and inspection program in the shop's quality control system (Section VIII Division 1, Mandatory Appendix 10), and inspections by the Authorized Inspector during construction (UG-90). Most purchasers of Code vessels, heat exchangers and boilers then ask for a job ITP with the bid or the purchase order, so their own inspector can mark the points they want to see.

What are hold, witness, review and surveillance points?

They are industry conventions, written on the ITP, for how much a party is involved at a step. ASME doesn't define them; the purchase order or the shop's procedure does.

Code on the ITPMeaningWhat happens on the floor
H, holdWork may not go past this step until the named party has inspected and released itThe next step is blocked; nobody starts it, whatever the schedule says
W, witnessThe party is given notice and may attend; if they don't come within the agreed notice, work goes onThe notice is recorded, then the step proceeds
R, reviewThe party reviews records (an MTR, a WPS, an NDE report), not the work itselfDocuments are sent or opened; work isn't held unless the review fails
S, surveillanceThe party may look in at any time without noticeNo stop, no notice

A step can carry a different code for each party: hold for shop QC, witness for the customer, review for the Inspector. That is why an ITP has one column per party.

What columns does an ITP need?

ColumnExample
Step number4.2
ActivityRT of long seam L1
Reference documentDrawing 1005-02 rev B; weld map; WPS-103
Acceptance criteriaThe Code paragraph or the customer specification, e.g. UW-51 for full radiography
Record producedRT report with film or digital image numbers
Shop QCH
Authorized InspectorR (or the points the Inspector has chosen)
Customer or third-party inspectorW
PrerequisitesSteps that must pass first, e.g. 4.1 VT of L1
Sign-offName, date, result, and the NCR number if it failed

The prerequisites column is the one paper ITPs leave implicit. It is what makes a failed step stop the right later steps and not the whole job.

What does an ITP for a heat exchanger look like?

A made-up shell-and-tube example (an ITP for a real job follows the customer's specification and your manual):

StepActivityQCAICustomer
1.1Drawing and calculation reviewRRR
2.1Material receipt: plate, tube, forgings against MTRsHRR
2.2Heat number transfer before cuttingHSS
3.1Shell long seam fit-upHSS
3.2Shell long seam welding to WPS, welder stamps recordedSSS
4.1VT of long seamHSS
4.2RT or UT of long seamHRR
5.1Nozzle fit-up and welding, reinforcement padsHSW
6.1Tubesheet drilling and dimensional checkHSW
6.2Tube-to-tubesheet joints: expansion or welding, leak testHWW
7.1PWHT, where required, with the chartHRR
8.1Hydrostatic test, shell side and tube sideHHW
9.1Final dimensional and visualHHW
9.2Nameplate stamping and data report signatureHHR
10.1Painting, preservation and shipping releaseHSH

The Inspector's points in practice: the Inspector decides what to inspect and when, within the shop's program, and always signs off the final inspection and the pressure test before the data report is certified.

Who decides the hold points?

Three parties, each for their own reasons:

  • Your quality control manual says where QC must release work (material receipt, fit-up before welding, NDE before closing a joint).
  • The Authorized Inspector chooses the stages they will inspect, and must be told when the work reaches them.
  • The purchaser adds witness and hold points through the purchase order or their own inspection specification, usually with a notice period. The ITP is often an attachment to the order and signed by both sides before work starts.

When the three disagree, the strictest wins at that step. Agree the ITP before material is cut, not after the first missed witness point.

How does a failed inspection affect the ITP?

It holds the steps that depend on it until the failure is closed. A failed RT on one seam should stop the work that would cover it up or rely on it (closing welds, PWHT, the hydro test) while the rest of the vessel goes on. The failure becomes a nonconformance report: disposition, repair to an approved repair WPS, re-examination by the same method, verification, close. The failed result stays on the record next to the pass that followed it.

Why do holds get skipped?

Because on paper a hold point is a box on a sheet, and the schedule is louder. The common failures:

  • The traveler and the ITP are separate papers, and the floor works from the traveler.
  • The customer's witness notice is sent by email and never confirmed, so nobody knows whether the step may proceed.
  • A repair is re-examined and passed, but the NCR is still open, and the next step starts anyway.
  • The ITP is revised by the customer mid-job and the floor still has the old copy.

An auditor or joint review team will pick a weld and ask to see its step on the ITP, its NDE, the welder and the release. ASME's handbook expects the shop to show its program working: "It is expected that fabrication functions be demonstrated using typical Code work."

Is there a free ITP template?

Yes: an inspection and test plan as Excel, Word, PDF, free under CC BY 4.0, with the columns above and eight sample steps from drawing review to the data report. The hold, witness and review points in the sample are an example only: the Inspector, the customer's specification and your quality manual set the real ones.

How can software enforce an ITP?

By making the hold real at the place work is started, not only on a screen. What to look for:

  • The ITP entered once as a template (one per product type), copied to each job, and revisable per job with the revision kept.
  • Each point carrying its type for each party, its prerequisites and the test it needs.
  • Starting a step refused by the server when a prerequisite hasn't passed or an NCR is open, with the reason shown.
  • Every attempt kept: a failed inspection stays visible after the re-inspection passes.
  • Witness notices recorded with their time, and the customer's release recorded with how it was given.
  • Shipping refused while any point or NCR is open.

Our US boiler demo does this. Its ITP templates carry R, W and H points with the points each depends on (an exchanger template has 60). On job AB-1005, RT failed on weld L1, so the server refuses to start the dependent step, and the screen says why; the NCR is dispositioned, the repair recorded, the weld re-inspected and passed, verified, closed and released, after which the step opens. Try it at the live demo (sample data) or read ERP for boiler and pressure vessel shops. The Inspector and the customer don't log in to sign points yet; their releases are recorded by the shop.

Quoted from the official text (2)

“It is expected that fabrication functions be demonstrated using typical Code work.”

ASME BPV-GUI-03, section 3

“a demonstration of implementation of the program”

ASME BPV-GUI-03, section 3

WPS and PQR registers, welder continuity, heat numbers from receipt to nameplate, and the data report package: the records a Code shop keeps, in one system.

A boiler manufacturer's system, from enquiry to dispatch and the IBR folder, with sample logins: try the live demo.

A boiler and pressure vessel shop's system, from inquiry to shipping and the ASME data report package, with sample logins: try the live demo. Fixed price, scope agreed before work starts: see the prices.

What this page is not

A guide written by Ahrom Labs, not engineering advice, and not yet reviewed by an Authorized Inspector. The ASME Code is copyrighted and sold by ASME: paragraphs are cited by number and explained in our own words, never reproduced. Check every figure against your copy of the 2025 Edition and with your Authorized Inspector before relying on it. Last updated .

Talk to us about your systems.

Tell us what's held together with workarounds right now. We reply to every message ourselves.