Over and under billing
The gap between what a contractor has billed on a job and what it has earned by percentage of completion: billing ahead of progress is over billing (a liability), behind it is under billing (an asset).
Pujan Motiwala · · Updated
It matters because it is the earliest warning that a job is losing money, and because banks and surety companies read it on the WIP schedule to judge a contractor. Percent complete is cost to date over estimated total cost; earned revenue is that share of the contract value; billings above it are over billing, below it under billing.
How a work-in-progress schedule finds both, with a worked example, is in the WIP schedule; the billing it is measured against is in pay applications.