Pay applications (AIA G702 and G703), explained
A pay application is a contractor's monthly bill on a construction job: each line of the schedule of values with the work completed before and this period, materials stored, the retainage held back, and the amount now due. AIA's G702 is the one-page summary and certificate; G703 is the line-by-line continuation sheet. The architect or owner certifies the amount before the owner pays.
Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

What goes into a pay application?
A pay application is the contractor's monthly bill against progress: for every line of the schedule of values it shows the work completed before this period, the work completed this period, materials stored, the total to date, the retainage held, and the amount now due. US construction contracts are usually paid this way rather than on milestones.
The American Institute of Architects (AIA) publishes the most used forms, G702 and G703. They are paid, copyrighted documents (AIA offers free partial samples of G702 and G703); many owners and general contractors use their own form with the same columns and arithmetic.
What is the difference between G702 and G703?
G702 is the summary: one page of totals that the contractor signs to apply for payment and the architect signs to certify it. G703 is the continuation sheet: one row per line of the schedule of values. AIA's instructions have the contractor fill in G703 first and carry its totals to G702, then sign G702 and send both to the architect.
| G702, Application and Certificate for Payment | G703, Continuation Sheet | |
|---|---|---|
| What it holds | Contract sum, change orders, totals, retainage, previous certificates, payment due | Each schedule of values line with its scheduled value, work and stored materials |
| Who signs | Contractor (application, notarized) and architect (certificate) | Nobody separately; it is attached to G702 |
| Change orders | Summarized in a change order box and line 2 | Usually listed as their own lines |
What is a schedule of values, and who prepares it?
The schedule of values is the contract sum broken into lines (general conditions, concrete, steel, electrical and so on) that every pay application bills against. The contractor prepares it and submits it to the architect at the start of the job, as the general conditions require; AIA doesn't publish a standard schedule of values form. AIA's instructions say the breakdown, whether by sections of work or by subcontractor, should stay consistent through the project.
Its total must equal the original contract sum. Owners and architects watch for front-loading: early items valued high so the contractor is paid ahead of the work. Agree the lines and values before the first application; changing them later is harder than getting them right.
How do you fill in G703, column by column?
| Column | Holds | Rule |
|---|---|---|
| A | Item number | |
| B | Description of work | |
| C | Scheduled value | Starts at the original contract sum; change orders are usually added as their own lines |
| D | Work completed, from previous application | Previous D plus previous E |
| E | Work completed, this period | Includes stored material from earlier periods now installed |
| F | Materials presently stored | Not in D or E; value moves to E as the material is installed |
| G | Total completed and stored to date | D + E + F, with % complete (G ÷ C) |
| H | Balance to finish | C − G |
| I | Retainage, if the rate varies by line | Only needed where variable retainage applies |
A worked G703 on a made-up $400,000 contract with one approved $20,000 change order, at the end of month three:
| Item | C Scheduled | D Previous | E This period | F Stored | G To date | % | H Balance |
|---|---|---|---|---|---|---|---|
| 1 General conditions | $40,000 | $12,000 | $4,000 | $16,000 | 40% | $24,000 | |
| 2 Concrete | $120,000 | $60,000 | $30,000 | $90,000 | 75% | $30,000 | |
| 3 Structural steel | $140,000 | $18,000 | $20,000 | $10,000 | $48,000 | 34% | $92,000 |
| 4 Electrical | $100,000 | $6,000 | $6,000 | 6% | $94,000 | ||
| CO 1 Added canopy | $20,000 | 0% | $20,000 | ||||
| Total | $420,000 | $90,000 | $60,000 | $10,000 | $160,000 | 38% | $260,000 |
How is retainage calculated on a pay application?
Retainage is a percentage of the work completed (columns D + E) plus a percentage of the materials stored (column F); the two rates can differ if the contract says so. G702 then takes it off the total to date and deducts what was certified before. With 10% on both, the totals above go onto G702 like this:
| G702 line | Calculation | Amount |
|---|---|---|
| 1 Original contract sum | $400,000 | |
| 2 Net change by change orders | $20,000 | |
| 3 Contract sum to date | Line 1 ± 2 | $420,000 |
| 4 Total completed and stored to date | G703 column G | $160,000 |
| 5a Retainage on completed work | 10% × (D + E) = 10% × $150,000 | $15,000 |
| 5b Retainage on stored material | 10% × F = 10% × $10,000 | $1,000 |
| 5 Total retainage | 5a + 5b | $16,000 |
| 6 Total earned less retainage | Line 4 − line 5 | $144,000 |
| 7 Less previous certificates for payment | Line 6 of the last certificate: $90,000 − $9,000 | $81,000 |
| 8 Current payment due | Line 6 − line 7 | $63,000 |
| 9 Balance to finish, including retainage | Line 3 − line 6 | $276,000 |
Check: this period's $60,000 of work plus $10,000 stored is $70,000; less 10% is $63,000. If the contract retains nothing on stored material, line 5b is zero and line 8 becomes $64,000. When retainage is reduced (for example at 50% complete), line 5 falls and the release shows up as extra payment on line 8, so the reduction must be written in the contract or approved in writing first.
Can you bill for stored materials?
Usually yes, if the contract allows it and you can prove the material exists and is yours to sell to the owner. Stored material goes in column F at its value; it is not deducted when the owner pays for it, only moved to column E as it is installed. Owners and lenders typically ask for the supplier's invoice, photos, proof of insurance, and for material stored off site, a bill of sale or other proof of title.
On federal jobs, FAR 52.232-5 lets the contracting officer count material delivered to the site. Material held elsewhere counts only if the contract specifically allows it and the contractor gives satisfactory evidence that it has acquired title and that the material will be used on the contract.
Does a G702 need to be notarized?
The G702 form has a notary block under the contractor's signature, and AIA's instructions say the contractor should sign it and have it notarized. Whether a notarized signature is legally required depends on the contract and the owner; many owners and lenders insist on it, some accept electronic signatures without it. Check the contract's payment section before the first application rather than finding out when it is returned.
What is a pencil draft, and when is a pay application due?
A pencil draft (or pencil copy) is an unsigned draft of the pay application sent to the owner's representative or architect a few days before the real one, so they can agree the percentages before anything is notarized. It is common practice, not something the AIA forms require. The contract sets the period the application covers, the day it is due each month and how long the owner has to pay; a late or rejected application usually waits for the next cycle, which can cost a month of cash.
On federal jobs the due date is set by FAR 52.232-27: a progress payment is due 14 days after the designated billing office receives a proper payment request, and a request that isn't proper must be returned within 7 days with the reasons.
Who approves a pay application, and can they approve less?
The architect (or the owner's representative where there is no architect) checks the application against the work on site and certifies the amount due, which may be less than applied for. AIA's instructions say the architect then initials every figure changed on G702 and G703 and attaches an explanation; the owner pays the amount certified. Lenders often want lien waivers from the contractor and from the subcontractors paid from the previous application before releasing money.
On federal jobs, FAR 52.232-5 sets the rules: progress payments monthly on estimates of work accomplished, approved by the contracting officer, with an itemization of the amounts by element of work, a listing of each subcontractor's work, subcontract value and previous payments, and a certification with every request or payment isn't made. The certification says, among other things, that subcontractors and suppliers have been paid from previous payments.
Why do pay applications get rejected?
Most rejections come from a handful of causes:
- The arithmetic doesn't tie. G703 totals don't match G702, or line 7 isn't line 6 of the last certificate.
- Percent complete ahead of the site. The architect sees less work in place than billed.
- Stored material without proof. No invoice, title or insurance, or it's off site without contract approval.
- Unapproved change orders billed. Only executed change orders belong in column C.
- Missing lien waivers for the previous payment, from the contractor or subcontractors.
- Missing signature, notarization or certification, or the wrong period.
- A changed schedule of values that no longer matches the approved one.
Each of these is cheaper to prevent with a pencil draft than to fix after the application is returned.
What should pay application software do?
When comparing systems, check that it can:
- Hold the schedule of values per job, locked once approved, with change orders added as their own lines.
- Take quantities or percentages from site progress, not typed in at month-end.
- Carry each certified application forward, so column D and line 7 always match what was certified, including any amount the architect cut.
- Compute retainage per line, with separate rates for work and stored material, and its reduction and release.
- Move stored material to installed when it is used, without double counting.
- Track the lien waivers owed per application, and block payment of a subcontractor until theirs is in.
- Produce the application in the owner's format, and keep each submitted and certified version.
- Feed the same figures to the WIP schedule, so billing and cost are compared per job.
Our US construction demo runs G702/G703-style pay applications on a schedule of values with 10% retainage, change orders and lien waivers per pay application; it has no WIP schedule.
Can pay applications go to QuickBooks?
Yes, if the system posts each one as an invoice on the right job. In our construction demo, connected to a QuickBooks Online sandbox company, each project becomes a job under its client in QuickBooks, and each pay application goes there as an invoice on that job when it is issued; payments follow when marked paid. Job reports in QuickBooks then match the project. How the connection works, and who calculates the sales tax, is in connecting QuickBooks Online.
Quoted from the official texts (8)
“The Government shall make progress payments monthly as the work proceeds”
FAR 52.232-5(b), progress payments
“An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.”
FAR 52.232-5(b)(1)(i), substantiation
“The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.”
FAR 52.232-5(b)(2)(ii), material stored off site
“Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made”
FAR 52.232-5(c), contractor certification
“All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification”
FAR 52.232-5(c)(2), contractor certification
“This certification is not to be construed as final acceptance of a subcontractor’s performance.”
FAR 52.232-5(c)(4), contractor certification
“The due date for making such payments is 14 days after the designated billing office receives a proper payment request.”
FAR 52.232-27(a)(1)(i)(A), due date for progress payments
“If the invoice does not comply with these requirements, the designated billing office must return it within 7 days after receipt”
FAR 52.232-27, prompt payment (improper invoices)
Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.
Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.
Official sources
- Instructions: G702–1992, Application and Certificate for Payment. AIA Contract Documents, November 5, 2026.
- Instructions: G703–1992, Continuation Sheet. AIA Contract Documents, November 5, 2026.
- Summary: G702–1992, Application and Certificate for Payment. AIA Contract Documents, November 5, 2026.
- G702–1992 Application and Certificate for Payment, free partial sample. AIA Contract Documents, November 5, 2026.
- G703–1992 Continuation Sheet, free partial sample. AIA Contract Documents, November 5, 2026.
- FAR 52.232-5, Payments Under Fixed-Price Construction Contracts. Acquisition.gov (General Services Administration), November 3, 2026.
- FAR 52.232-27, Prompt Payment for Construction Contracts. Acquisition.gov (General Services Administration), November 3, 2026.
What this page is not
A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .
Talk to us about your systems.
Tell us what's held together with workarounds right now. We reply to every message ourselves.