Performance guarantee, security deposit and defect liability

On a CPWD work the contractor gives a performance guarantee, usually 5% of the tendered amount as a bank guarantee or other listed instrument, valid to the stipulated completion date plus at least 6 months, and returned after the completion certificate. Security deposit, 2.5%, is deducted from bills and refunded after the defect liability period, 12 months from completion (6 months on works up to ₹10 lakh), or once the final bill is passed.

Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

A rolled document tied with a navy ribbon on a closed hardbound contract, a brass padlock beside it: a bank guarantee securing the contractor's obligations.

What is a performance guarantee?

A performance guarantee is security the contractor gives the client, at the start of the contract, that it will perform the contract; the client can claim it if the contractor doesn't. On CPWD works, Clause 1 of the General Conditions of Contract 2023 requires an irrevocable performance guarantee at the percentage in Schedule E of the tendered amount, on top of the other deposits in the contract, within the period Schedule F allows after the letter of acceptance. Schedule E of GCC 2023 sets it at 5% of the tendered value.

In what form can a performance guarantee be given?

As an insurance surety bond, an account payee demand draft, a fixed deposit receipt, or a bank guarantee from any commercial bank, under Clause 1. If a bank can't pay against a fixed deposit receipt given as part of the guarantee, the loss falls on the contractor, who must make it good on demand.

How long must a performance guarantee be valid?

Up to the stipulated date of completion plus at least 6 months, and longer if the time for completion is extended: the contractor must get its validity extended to cover the extended time. If it doesn't, the Engineer-in-Charge may claim the full amount. The CPWD Works Manual 2022 put it differently (valid at least sixty days beyond completion of all contractual obligations), and CPWD amended Clause 1 and Schedule E by a circular on 27 February 2026; check the version of the GCC your contract names.

When is the performance guarantee returned or forfeited?

It's returned, without interest, once the competent authority records the completion certificate. The client can claim it only for amounts it's entitled to under the contract: the full amount if the contractor fails to extend its validity, or an amount the contractor owes and hasn't paid within 30 days of a notice. If the contract is determined or rescinded, the whole guarantee is forfeited. On contracts that include maintenance after construction, half of it is kept as security deposit and returned year by year.

What is the difference between a performance guarantee and a security deposit?

The performance guarantee is given once, up front, and returned at completion; the security deposit is built up from the bills and kept until the defect liability period has run. On CPWD works, 2.5% of the gross amount of each running and final bill is deducted until the deposit reaches 2.5% of the tendered amount (Clause 1A). Private contracts call it retention money and set their own rate; see RA bills for how it comes off each bill.

Performance guaranteeSecurity deposit
Amount (CPWD)5% of tendered value2.5% of tendered value
How givenUp front: bank guarantee, surety bond, FDR or DDDeducted from each running and final bill
ReturnedAfter the completion certificateAfter the defect liability period, or when the final bill is passed, whichever is later

Can the security deposit be released against a bank guarantee?

Yes. Under Clause 1A, the security deposit deducted from bills can be released against a bank guarantee from a scheduled bank once at least ₹5 lakh has built up; each guarantee except the last must be for at least ₹5 lakh, and its validity must follow Clause 17 and any extension of time. That frees cash during the job, using the contractor's bank guarantee limits instead.

What is the defect liability period?

The time after completion during which the contractor must make good, at its own cost, defects that appear in the work from faulty materials or workmanship: twelve months after the completion certificate, or six months for works costing ₹10 lakh or less (except road works), under Clause 17. If the contractor doesn't fix them after written notice, the Engineer-in-Charge can have them fixed by others and recover the cost from any money due to the contractor or from the security deposit.

When is the security deposit refunded?

Not before the defect liability period ends, or until the final bill has been prepared and passed, whichever is later. For road works, half may be refunded after six months and the rest after twelve, if the Engineer-in-Charge thinks half is enough to cover the contractor's liabilities. CPWD issued an advisory on releasing security deposit on 18 November 2025; ask the division for the current procedure.

What does this look like on a ₹2 crore work?

A made-up CPWD work with a tendered amount of ₹2,00,00,000, stipulated completion 31 December 2026, actual completion certificate 15 January 2027 (within an extension granted):

ItemAmountHeld until
Performance guarantee, 5% (bank guarantee)₹10,00,000Completion certificate (15 January 2027); validity at least 6 months beyond the extended completion date
Security deposit, 2.5%, from bills₹5,00,00015 January 2028, or when the final bill is passed, if later
Security deposit released against a bank guarantee₹5,00,000The guarantee then stays in place instead of the cash

How should a contractor track guarantees and deposits?

  • Every bank guarantee with its amount, purpose (performance, security deposit, mobilisation advance), bank, expiry and the date it must be extended to.
  • Security deposit deducted per bill, the running total against the cap, and any release against a guarantee.
  • The completion certificate date, the defect liability period, defects notified and fixed, and the refund date.
  • Bank guarantee commission and limits used, per job.

The CPWD Works Manual itself asks divisions to monitor bank guarantees given for earnest money, performance, security deposit, mobilisation advance and milestones; a contractor needs the same list from its side. The construction demo doesn't track bank guarantees, security deposits or the defect liability period yet; those are parts we'd build, from the same RA bills and completion dates. For the price side of a long contract, see the price escalation clause.

Quoted from the official texts (13)

“The contractor shall submit an irrevocable Performance Guarantee at specified percentage of the tendered amount as mentioned in Schedule 'E'”

GCC 2023, Clause 1(i) (performance guarantee)

“This Guarantee shall be in the form of Insurance Surety Bonds, Account Payee Demand Draft, Fixed Deposit Receipt or Bank Guarantee from any of the Commercial Banks.”

GCC 2023, Clause 1(i) (forms)

“shall be initially valid up to the stipulated date of completion plus minimum 6 months beyond that.”

GCC 2023, Clause 1(ii) (validity)

“After recording of the completion certificate for the work by the competent authority, the performance guarantee shall be returned to the contractor, without any interest.”

GCC 2023, Clause 1(ii) (return)

“Failure by the contractor to extend the validity of the Performance Guarantee as described herein above, in which event the Engineer-in-Charge may claim the full amount of the Performance Guarantee.”

GCC 2023, Clause 1(iii)(a)

“In the event of the contract being determined or rescinded under provision of any of the Clause/Condition of the agreement, the performance guarantee shall stand forfeited in full”

GCC 2023, Clause 1 (forfeiture on determination)

“(ii) Performance Guarantee : 5% of tendered value. (iii) Security Deposit : 2.5% of tendered value.”

GCC 2023, Schedule E

“to deduct a sum at the rate of 2.5% of the gross amount of each running and final bill till the sum deducted will amount to security deposit of 2.5% of the tendered amount of the work.”

GCC 2023, Clause 1A (security deposit)

“The security deposit as deducted above can be released against bank guarantee issued by a scheduled bank, on its accumulations to a minimum of Rs. 5 lac”

GCC 2023, Clause 1A

“if any defect, shrinkage or other faults appear in the work within twelve months (six months in the case of work costing Rs. Ten lacs and below except road work) after a certificate final or otherwise of its completion”

GCC 2023, Clause 17 (defect liability)

“The security deposit of the contractor shall not be refunded before the expiry of twelve months (six months in the case of work costing Rs. Ten lacs and below except road work) after the issue of the certificate final or otherwise, of completion of work, or till the final bill has been prepared and passed whichever is later.”

GCC 2023, Clause 17 (refund of security deposit)

“PG shall be 5% of the contract amount or as prescribed from time to time”

CPWD Works Manual 2022, para 5.2(2)

“The bank guarantee submitted by agencies for various purposes such as earnest money deposit/ performance guarantee/security deposit/ mobilization advance/ Milestone(s) shall be effectively monitored.”

CPWD Works Manual 2022, para 5.5.3 (bank guarantees)

Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.

Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.

Official sources

What this page is not

A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .

Talk to us about your systems.

Tell us what's held together with workarounds right now. We reply to every message ourselves.