RA bills: deductions, advances and the final bill
A running account (RA) bill is a contractor's interim bill for work measured so far, paid as an advance against the final bill while the work goes on. Each is drawn from the measurement book, to date less earlier bills, with GST on top and deductions taken off: security deposit (2.5% of each bill on CPWD works), TDS, GST TDS on government work, and recovery of any mobilisation or secured advance. The final bill closes the contract.
Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

What is an RA bill?
A running account (RA) bill is an interim bill for the work measured so far, paid while the work continues; the final bill closes the contract. On an item-rate contract the contractor is paid by measured quantity at the agreed rate for each BOQ item, so the work is billed in stages: the 1st RA bill, the 2nd, and so on. CPWD's general conditions treat every such payment as an advance against the final payment, so an RA bill doesn't mean the work has been accepted. Most private contracts in India follow the same pattern, with the rates and deductions their own contract sets.
How is an RA bill calculated?
From the measurement book, cumulatively: the value of all work measured to date at the agreement rates, plus approved extra and deviated items, less the gross of all earlier bills. The deductions are then taken from this bill's value.
| Line | Example (made up) |
|---|---|
| Value of work done to date, item by item at agreement rates | ₹48,00,000 |
| Add: extra and deviated items approved | ₹1,50,000 |
| Gross value to date | ₹49,50,000 |
| Less: gross of previous RA bills | ₹31,00,000 |
| Gross value of this bill | ₹18,50,000 |
Which works are paid by RA bills on CPWD contracts?
Works estimated to cost more than ₹20 lakh. Under Clause 7 of CPWD's General Conditions of Contract 2023, a work estimated at ₹20 lakh or less is paid only after the whole work is completed and the completion certificate given. Bigger works are billed monthly on recorded measurements, on the date the Engineer-in-Charge fixes, and a bill is due only once the work done since the last one reaches the minimum set in the contract's Schedule F.
What is deducted from an RA bill?
Up to five things, each set by the contract or the law:
- Security deposit (retention money): a percentage of each bill held until the defects period ends.
- Income-tax TDS at 1% or 2%: see TDS on payments to contractors.
- GST TDS, when the client is a government department or agency: 1% CGST plus 1% SGST; see GST on works contracts.
- Recovery of advances: mobilisation advance with its interest, and secured advance once the material is used.
- Recoveries for materials the client issued, water, electricity, and any penalties the contract allows.
How much security deposit is deducted from an RA bill?
On CPWD works, 2.5% of the gross amount of each running and final bill, until 2.5% of the tendered amount has been held (GCC Clause 1A). On a ₹2 crore work that is ₹5 lakh in all; a ₹18,50,000 bill gives up ₹46,250. Private contracts usually call it retention money and set their own rate. CPWD lets the deposit be released against a bank guarantee from a scheduled bank once at least ₹5 lakh has built up.
When is the security deposit refunded?
After the defect liability period, or once the final bill is passed, whichever is later. Under GCC Clause 17 that period is 12 months after the completion certificate, or 6 months for works costing ₹10 lakh or less (except road works); the contractor must make good defects that appear in it, and the department can pay for them from the deposit. Clause 1 and the release of security deposit have been amended by CPWD circulars since 2023; check the contract's own GCC version.
What is a mobilisation advance, and how is it recovered?
An advance to set up the work (site office, labour camp, testing lab, godown, plant and machinery, shuttering), up to 10% of the tendered amount, when the contract provides for it. Under GCC Clause 10B it's asked for in writing within six months of the order to start, paid in instalments of no more than 5% each (the next only after the last is shown to be used), and carries simple interest at 8% a year. Recovery starts once 10% of the work's gross value has been executed and paid, in proportion to each bill, so that all of it is back by the time 80% has been executed and paid.
On a ₹2 crore work with a ₹20 lakh advance, recovery runs over the ₹1.4 crore of work between 10% and 80%: 14.29% of each bill's gross value. Interest is charged on the amount still outstanding up to each recovery.
What is a secured advance?
An advance on materials brought to site for work not yet done: up to 75% of the assessed value of materials that are non-perishable, non-fragile and non-combustible, properly stored and not yet built in (GCC Clause 10B). When the material is used in the work, the advance is recovered from the next payment. It isn't paid on high-risk materials such as ordinary glass, sand, petrol or diesel; perishable or fragile materials qualify only with insurance and the Engineer-in-Charge's approval. Cement and steel on site assessed at ₹4,00,000 give an advance of ₹3,00,000, recovered in full from the bill in which they are built in.
What does a full RA bill look like with every deduction?
RA bill #3 on a made-up ₹2 crore CPWD-style work, contractor a company, client a government department:
| Line | ₹ |
|---|---|
| Gross value of this bill | 18,50,000 |
| Add GST at 18% (the contractor's tax invoice) | 3,33,000 |
| Invoice value | 21,83,000 |
| Less security deposit, 2.5% of the gross | 46,250 |
| Less mobilisation advance recovered (14.29% of the gross) | 2,64,286 |
| Less interest on the advance outstanding (₹18,42,857 × 8% × 31 days) | 12,521 |
| Less income-tax TDS at 2% on the value excluding GST | 37,000 |
| Less GST TDS, 1% CGST + 1% SGST | 37,000 |
| Net payable | 17,85,943 |
The figures are made up; the days of interest are illustrative. Recovery of the advance started on bill #2, so ₹1,57,143 of it had already come back.
How soon must an RA bill be paid?
On CPWD works, at least 75% of the net bill as an ad-hoc payment within 10 working days of submission, and the rest after final checking within 28 working days (GCC Clause 7). If a bill that's in order isn't paid within 45 days of submission, the department pays simple interest at 5% a year from the end of the time limit. On the bill above, the ad-hoc payment is at least ₹13,39,457.
For a private client: if you're a registered micro or small enterprise, the MSMED Act caps the agreed credit period at 45 days from acceptance; see the MSME payment rule.
When must the final bill be submitted and paid?
Within three months of physical completion, or one month of the final completion certificate, whichever is earlier (GCC Clause 9). Once it's submitted, no further claims can be made: they are treated as waived. The undisputed items, and disputed ones at the approved quantity and rate, are paid within three months of the bill being received, with 5% a year interest if the department is late on a bill submitted in time. Work completed on 15 January 2027 with the final certificate on 10 March 2027 needs its final bill by 10 April 2027.
Can I get paid before the work is measured?
Sometimes. The CPWD manual allows advance payments on a running bill for work measured but not yet checked, or done but not yet measured, on conditions, adjusted when the measurements are recorded. GCC Clause 7 also lets the Engineer-in-Charge pay 75% of the assessed value of a building floor's work up to lintel or slab level without detailed measurement, adjusted in the next bill.
Is there a free RA bill format in Excel?
Yes: the RA bill format (Excel, free under CC BY 4.0; also as a blank Word file and PDF to print). One sheet per bill, with each BOQ item's quantity up to the previous bill, this bill and up to date, the amounts for each, and this bill's GST, security deposit, TDS, labour cess and mobilisation advance recovery down to the net payable. The rates are typed in, so set them to your contract; the worked example is made up. Pair it with the measurement book format.
What should a contractor's system track on RA bills?
- The BOQ with agreement rates, and each RA bill taken from the measurements, never typed totals.
- Every bill cumulative, so this bill is always to date less previous.
- Each deduction by type across bills: security deposit held, advances still to recover with their interest, TDS and GST TDS deducted.
- Extra and deviated items kept apart until approved, so they're billed once.
- Due dates for the ad-hoc payment, the balance and the final bill, and the refund date of the security deposit.
The construction demo builds each RA bill from measurements against the BOQ (previous, this bill and up to date per line, the GST split and the amount in words, as a PDF), moves it from draft to submitted, certified and paid, and flags quantities beyond the BOQ. It doesn't yet take security deposit, TDS, GST TDS or advance recoveries off the bill, or produce a separate final bill; those are parts we'd build.
Quoted from the official texts (22)
“to deduct a sum at the rate of 2.5% of the gross amount of each running and final bill till the sum deducted will amount to security deposit of 2.5% of the tendered amount of the work.”
GCC 2023, Clause 1A (recovery of security deposit)
“The security deposit as deducted above can be released against bank guarantee issued by a scheduled bank, on its accumulations to a minimum of Rs. 5 lac”
GCC 2023, Clause 1A
“No payment shall be made for work, estimated to cost Rs. twenty lacs or less till after the whole of the work shall have been completed and certificate of completion given.”
GCC 2023, Clause 7 (running bills)
“An amount of ad-hoc payment not less than 75% of the net amount of the bill under check, shall be made within 10 working days of submission of the bill”
GCC 2023, Clause 7
“The remaining payment is also to be made after final checking of the bill within 28 working days of submission of bill by the contractor.”
GCC 2023, Clause 7
“a simple interest @ 5% (five percent) per annum shall be paid to the contractor from the date of expiry of prescribed time limit.”
GCC 2023, Clause 7
“All such interim payments shall be regarded as payment by way of advances against final payment only”
GCC 2023, Clause 7
“within three months of physical completion of the work or within one month of the date of the final certificate of completion furnished by the Engineer-in-Charge whichever is earlier.”
GCC 2023, Clause 9 (final bill)
“No further claims shall be made by the contractor after submission of the final bill and these shall be deemed to have been waived and extinguished.”
GCC 2023, Clause 9
“up to 75% of the assessed value of any materials, which are in the opinion of the Engineer-in- charge non-perishable, non-fragile and non-combustible”
GCC 2023, Clause 10B(i) (secured advance)
“When materials on account of which an advance has been made under this subclause are incorporated in the work, the amount of such advance shall be recovered/deducted from the next payment made under any of the clause or clauses of this contract.”
GCC 2023, Clause 10B(i)
“No secured advance, shall however, be paid on high-risk materials such as ordinary glass, sand, petrol, diesel.”
GCC 2023, Clause 10B(i)
“Mobilization advances not exceeding 10% of the tendered amount may be given, if requested by the contractor in writing within six months of the order to commence the work.”
GCC 2023, Clause 10B(ii) (mobilisation advance)
“The amount of any installment shall not exceed 5% of the tendered amount of the work.”
GCC 2023, Clause 10B(ii)
“The mobilization advance in (ii) above bear simple interest at the rate of 8 percent per annum”
GCC 2023, Clause 10B(iii)
“Recovery of such sums advanced shall be made by the deduction from the contractors bills commencing after first ten percent of the gross value of the work is executed and paid”
GCC 2023, Clause 10B(iii)
“the entire advance is recovered by the time eighty percent of the gross value of the contract is executed and paid”
GCC 2023, Clause 10B(iii)
“The security deposit of the contractor shall not be refunded before the expiry of twelve months (six months in the case of work costing Rs. Ten lacs and below except road work) after the issue of the certificate final or otherwise, of completion of work, or till the final bill has been prepared and passed whichever is later.”
GCC 2023, Clause 17 (defect liability and refund of security deposit)
“The security deposit shall be deducted from the running bill as well as final bill as per provisions of the GCC.”
CPWD Works Manual 2022, para 5.5 (security deposit)
“Secured advance is a term applied specifically to an advance made on the materials brought at site of work, to a contractor whose contract is for the completed item of work.”
CPWD Works Manual 2022, para 5.10 (secured advance)
“All measurements are to be done as per provisions of GCC and abstract of schedule of measurements and payments are to be entered through PFMS portal of CPWD using E-MB module.”
CPWD Works Manual 2022, para 5.12 (measurement of work)
“Provided that in no case the period agreed upon between the supplier and the buyer in writing shall exceed forty-five days from the day of acceptance or the day of deemed acceptance.”
MSMED Act, 2006, section 15
Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.
Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.
Official sources
- General Conditions of Contract 2023, Construction Works (with DG CPWD's office memorandum of 22.09.2023). Central Public Works Department, Government of India (copy published by IIT Kanpur), September 22, 2023.
- CPWD circulars: General Conditions of Contract (amendments to GCC 2023). Central Public Works Department, November 5, 2026.
- CPWD Works Manual 2022. Central Public Works Department, Government of India (copy published by NDMC), June 30, 2022.
- Micro, Small and Medium Enterprises Development Act, 2006. Gazette of India (Ministry of MSME copy), June 16, 2006.
What this page is not
A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .