Prompt payment acts: how fast contractors must be paid
Prompt payment laws set how fast each tier must pay and what it owes if it's late. On federal jobs a progress payment is due 14 days after a proper request and subs are paid within 7 days of the prime. In Texas a private owner pays within 35 days and the contractor pays subs within 7; California sets 30 days and 7; New York 30 days after approval and 7. Late money carries interest, often 1% to 2% a month.
Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

What is a prompt payment act?
A prompt payment act is a law that sets how quickly an owner must pay its contractor, and each contractor its subs and suppliers, and what is owed when a payment is late. The federal government has one for its own contracts, and many states have their own, some for public jobs only and some for private jobs too. The contract usually sets the billing cycle; the act puts a ceiling on how long payment can take and adds interest or a penalty after it.
How fast must the federal government pay a contractor?
Within 14 days after the designated billing office receives a proper payment request for a progress payment, under FAR 52.232-27 and the Prompt Payment Act (31 U.S.C. 3903); interest runs on an approved payment left unpaid after that. The prime must pay its subs for satisfactory work within 7 days of being paid (31 U.S.C. 3905), and the subcontract must say so.
What are the deadlines in Texas, California, New York and Florida?
| State | Owner pays the contractor | Contractor pays its subs | If late |
|---|---|---|---|
| Texas, private | 35 days after a written payment request (Property Code 28.002) | 7 days after receiving the owner's payment | 1.5% a month (28.004) |
| Texas, public | Overdue on the 31st day after the later of delivery, completion or invoice (Government Code 2251.021) | 10 days after receiving payment (2251.022) | As chapter 2251 sets |
| California, private | 30 days after notice demanding payment, unless agreed otherwise in writing (Civil Code 8800) | 7 days after each progress payment, unless agreed otherwise in writing (Business and Professions Code 7108.5) | 2% a month, owner and contractor alike |
| New York, private, $150,000 and up | Approve or reject within 12 business days; pay within 30 days of approval (General Business Law 756-a) | 7 days after receiving good funds, once documents and waivers are in | As article 35-E sets |
| Florida, private | When the contract says, once the request, payment from above and waivers are in (Statutes 715.12) | Same rule, once the contractor has been paid for that work | Statutory rate plus 12% a year, from the 14th day after due |
| Florida, public | Undisputed portion by the contract date or 20 business days after the request, whichever is earlier (255.073) | 10 days after the contractor is paid; 7 days for a sub paying its subs | As the statute sets |
These are the main payment deadlines only; each act has its own exceptions, definitions and project thresholds.
Can an owner hold back part of a payment?
Yes, for a good-faith dispute, but only so much. In California an owner may withhold no more than 150% of the disputed amount from a progress payment, and a contractor the same from its sub. In Texas the withholding in a good-faith dispute is capped at the difference in dispute (110% of it on detached homes up to a quadruplex). In New York an owner who rejects part of an invoice must say in writing which items aren't approved and why.
How is interest on a late payment worked out?
At the statute's rate, from the day after the payment was due. A $43,200 progress payment on a Texas private job, due 35 days after the request and paid a month late, carries 1.5% for that month: $648. In California the same amount wrongfully withheld for a month costs the owner 2%, $864. Florida's private-job rate is the statutory judgment rate plus 12% a year, starting 14 days after the payment was due.
Can a contractor stop work if it isn't paid?
In some states, after notice. In Texas a contractor or sub may suspend work on the 10th day after giving the owner (and the lender, where required) written notice that an undisputed payment hasn't been received; that right doesn't apply to single-family homes up to a quadruplex or to public jobs. In New York a contract clause saying a party can't suspend work when the other doesn't pay promptly is void (General Business Law 757).
Do prompt payment rules cover retainage?
Usually, with their own deadlines. In California the owner pays retention within 45 days after completion and the contractor passes each sub's share on within 10 days of receiving it (Civil Code 8812, 8814); in New York retainage is released within 30 days of final approval. See retainage for each state's caps.
Can the contract override the prompt payment law?
Partly, and less than most contractors think. California's 30-day and 7-day rules give way to a different written agreement; Texas makes an attempted waiver of chapter 28 void, apart from a longer period allowed on single-family homes; in New York the contract governs except where the article says otherwise, and payment terms that differ from its payment sections are void. Read the contract's payment clause against the state's act before signing.
What should a contractor track to enforce prompt payment?
The dates the law counts from, per pay application: when the request was delivered, when it was approved, when the owner paid, and when each sub was paid from it. With those, the system can flag a late payment, work out the interest, and show that you paid your own subs on time, which matters when you are the one being chased.
- The date each pay application was submitted and approved.
- Payments received against each application, and payments made to each sub from it.
- The state of the project, so the right deadline and rate apply.
- Disputed items, with the written reason, kept apart from undisputed amounts.
In the construction demo, receivables are aged from the due date (not due, 1–30, 31–60, 61–90, over 90 days), each overdue bill becomes a weekly follow-up for its project manager, and anything past 30 days goes to the director. It doesn't work out statutory interest or track the deadline for paying each sub; those are parts we'd build. Missed deadlines also matter for liens: see mechanics lien deadlines.
Quoted from the official texts (20)
“The due date for making such payments is 14 days after the designated billing office receives a proper payment request.”
FAR 52.232-27(a)(1)(i)(A)
“a period of more than 14 days after receipt of the payment request by the place or person designated by the agency to first receive such requests”
31 U.S.C. 3903(a)(6)(A)(i)
“a payment clause which obligates the prime contractor to pay the subcontractor for satisfactory performance under its subcontract within 7 days out of such amounts as are paid to the prime contractor by the agency under such contract”
31 U.S.C. 3905(b)(1)
“not later than the 35th day after the date the owner receives the request.”
Texas Property Code 28.002(a)
“The payment required by this subsection must be made not later than the seventh day after the date the contractor receives the owner's payment.”
Texas Property Code 28.002(b)
“An unpaid amount bears interest at the rate of 1-1/2 percent each month.”
Texas Property Code 28.004(b)
“A vendor who receives a payment from a governmental entity shall pay a subcontractor the appropriate share of the payment not later than the 10th day after the date the vendor receives the payment.”
Texas Government Code 2251.022(a)
“the owner shall pay the direct contractor, within 30 days after notice demanding payment pursuant to the contract is given, any progress payment due as to which there is no good faith dispute between them.”
California Civil Code 8800(a)
“the owner may withhold from the progress payment an amount not in excess of 150 percent of the disputed amount.”
California Civil Code 8800(b)
“An owner that violates this section is liable to the direct contractor for a penalty of 2 percent per month on the amount wrongfully withheld”
California Civil Code 8800(c)
“A prime contractor or subcontractor shall pay to any subcontractor, not later than seven days after receipt of each progress payment, unless otherwise agreed to in writing”
California Business and Professions Code 7108.5(a)
“a penalty, payable to the subcontractor, of 2 percent of the amount due per month for every month that payment is not made.”
California Business and Professions Code 7108.5(b)
“within 10 days after receiving all or part of a retention payment, pay to each subcontractor from whom retention has been withheld that subcontractor's share of the payment.”
California Civil Code 8814(a)
“Upon delivery of an invoice and all contractually required documentation, an owner shall approve or disapprove all or a portion of such invoice within twelve business days.”
New York General Business Law 756-a(2)(a)(i)
“Payment of an interim or final invoice shall be due from the owner not later than thirty days after approval of the invoice.”
New York General Business Law 756-a(3)(a)(ii)
“seven days after receipt of good funds for each interim or final payment, provided all contractually required documentation and waivers are received.”
New York General Business Law 756-a(3)(b)(ii)
“stating that a party to the contract cannot suspend performance under the contract if another party to the contract fails to make prompt payments under the contract.”
New York General Business Law 757(2)
“shall bear interest at the rate specified in s. 55.03 plus an additional 12 percent per annum, computed beginning on the 14th day after payment is due pursuant to subsection (4).”
Florida Statutes 715.12(5)(a)
“the undisputed portion must be paid by the date required under the contract or by 20 business days after receipt of the request, whichever is earlier.”
Florida Statutes 255.073(2)
“the contractor shall remit payment due to those subcontractors and suppliers within 10 days after the contractor’s receipt of payment.”
Florida Statutes 255.073(3)
Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.
Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.
Official sources
- FAR 52.232-27, Prompt Payment for Construction Contracts. Acquisition.gov (General Services Administration), November 3, 2026.
- 31 U.S.C. 3903 and 3905, Prompt Payment Act. Legal Information Institute, Cornell Law School, November 5, 2026.
- Texas Property Code chapter 28 and Government Code chapter 2251. Texas Legislature, November 5, 2026.
- California Civil Code 8800, 8812, 8814 and Business and Professions Code 7108.5. California Legislative Information, November 5, 2026.
- New York General Business Law 756, 756-a and 757. New York State Senate, November 5, 2026.
- Florida Statutes 715.12 and 255.073. The Florida Legislature, November 5, 2026.
What this page is not
A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .