Submittals and RFIs: how they flow and what to log

A submittal is something the contractor sends for the design team's review before building or buying: shop drawings, product data, samples. An RFI (request for information) is a question about the contract documents, sent when the drawings or specifications are unclear or conflict. Both need a log with numbers, dates, ball-in-court and answers, because late or unanswered ones are a common source of delay and change order claims.

Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

Rolled shop drawings tied with string beside a stamped transmittal sheet and a hard hat: construction submittals.

What is a submittal?

A submittal is a document or sample the contractor sends to the architect or engineer, through the general contractor, to show what it intends to install before it buys or fabricates it. The specifications list what each trade must submit, usually in a "submittals" article of each section:

TypeExamples
Shop drawingsFabrication drawings for steel, ductwork, piping spools, millwork
Product dataManufacturer cut sheets for valves, fixtures, equipment
SamplesFinishes, colors, materials
Mock-upsA built sample of a wall or finish
Test reports and certificatesMill certificates, welding qualifications, test results
Closeout submittalsWarranties, O&M manuals, as-builts, attic stock

How is a submittal reviewed?

The sub sends it to the general contractor, who checks it against the contract and stamps it; the GC forwards it to the architect, who sends it to the engineer of record where needed; it comes back with a review action. Common stamps:

ActionMeaningWhat the sub does
Approved, or No exceptions takenProceedRelease for fabrication
Approved as noted, or Make corrections notedProceed with the correctionsFabricate with the notes; resubmit only if asked
Revise and resubmitNot acceptable as isCorrect and submit again
RejectedDoesn't meet the documentsSubmit a different product or design

The review confirms general conformance with the design intent; it doesn't move responsibility for dimensions and coordination off the contractor, and an approved submittal doesn't change the contract unless the change is processed as one.

What is an RFI?

A request for information: a written question about the drawings or specifications, sent when they are unclear, missing a detail, or conflict with each other or with site conditions. A good RFI asks one question, cites the sheet and detail, proposes an answer, and says what it holds up and by when it is needed.

When does an RFI become a change order?

When the answer adds work, changes work, or delays the job. An RFI answer that says "provide additional blocking" or "relocate per sketch" is a change to the contract documents, and the contractor should give notice and price it under the contract's changes clause before doing the work. Track the RFI number on the change order request so the link is clear. See change orders.

What should a submittal and RFI log contain?

ColumnWhy
Number and revision (e.g. 23 05 00-003 rev 1)Unique and tied to the spec section
Description and spec sectionWhat it is
Dates: sent, required back, returnedTurnaround against the contract's review period
Ball in courtWho has it now
Status and review actionOpen, approved, revise and resubmit
Lead time after approvalWhen material can arrive
Linked itemsChange order requests, schedule activities, purchase orders

The log is how a sub proves delay: if a submittal sat with the architect for six weeks against a two-week review period, the dates show it. A log with no dates proves nothing.

How do submittals affect the schedule?

Long-lead items (switchgear, air handlers, fabricated steel, elevators) can't be ordered until approved, so the submittal date drives delivery. Work back from the install date: install date − delivery lead time − fabrication time − review time (including one resubmittal) = the date the submittal must go in. Put those dates in the schedule.

Can you show an RFI that gets answered quickly?

RFI 017, Level 3 corridor ceiling height. Drawing A-301 detail 4 shows the corridor ceiling at 9'-0" AFF. Mechanical drawing M-203 shows the main supply duct with its bottom at 8'-10" in the same corridor between grid lines C and E. Proposed solution: lower the ceiling to 8'-6" between C and E only, keeping 9'-0" elsewhere. Please confirm or advise by 14 March; ceiling framing on Level 3 starts 18 March. Cost or time impact: none expected if the proposed solution is accepted.

One question, two sheet references, a proposed answer, a date it is needed by and why, and a statement on cost and time. Compare "Please clarify ceiling heights on Level 3", which will come back with a question.

What turnaround should you expect?

The contract usually sets it: review periods for submittals (often 10 to 14 days, longer for complex shop drawings or when the engineer of record must review) and response times for RFIs (often 5 to 10 days). Put the contract's numbers in your log so overdue items show automatically, and send a reminder before the date, not after the work has stopped. When a late answer delays your work, note it at the time with the RFI number; that note is what supports a time extension later.

What is a submittal register?

The list, made at the start of the job, of every submittal the specifications require from your trade: spec section, item, type, the date it is needed back to meet the schedule, and the lead time after approval. Building it from the specifications in the first two weeks catches the long-lead items early and avoids the classic failure: a required submittal nobody noticed until the inspector asks for it.

Who is responsible if an approved submittal is wrong?

Usually the contractor. Review stamps typically say the review is for general conformance with the design intent and doesn't relieve the contractor of responsibility for dimensions, quantities, coordination and compliance with the contract documents. If you submit a product that deviates from the specification, say so clearly in the submittal; a deviation buried in a cut sheet and approved without comment is still your deviation.

Is there a free submittal log and RFI log?

Yes, both in Excel, free under CC BY 4.0: a submittal log and an RFI log. Each has the columns above and works out the days in review or days open from the dates, which is the figure a delay claim rests on. The sample rows are made up.

Does our construction software handle submittals and RFIs?

Not yet. Our US construction demo covers daily field reports, pay applications with retainage, change orders, lien waivers, crews and payroll and job cost (see software for subcontractors and specialty contractors); a submittal and RFI log with ball-in-court and links to change order requests is something we would build on the same job records. See also pay applications.

Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.

Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.

Official sources

    What this page is not

    A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .