Retainage in construction: rates, state caps and release
Retainage is a share of each progress payment, often 5% or 10%, that the owner holds back until the work is complete, as security that the contractor finishes and fixes defects; the general contractor usually holds the same from its subs. Several states cap it at 5%, including California and New York on private jobs, and set a deadline to release it after completion. On federal jobs it is withheld only for unsatisfactory progress.
Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

What is retainage in construction?
Retainage (also called retention) is part of each progress payment that the owner holds back until the job is finished, as security that the contractor completes the work and fixes defects. Each pay application bills the work completed and stored to date, takes off the retainage percentage, and the balance is paid. The amount held builds up over the job and is paid at the end. The general contractor usually holds the same percentage from each subcontractor, so retainage runs down the whole chain.
How much retainage is normal?
Often 5% or 10% of each payment, as the contract sets it, and less where the state caps it. Some contracts lower the rate later in the job; federal rules allow the amount withheld to be adjusted as the contract nears completion. Agree the rate before the job starts and read the contract's retainage clause before you sign it.
A made-up $400,000 job at 10%, at the end of month three:
| Line | Amount |
|---|---|
| Work completed to date | $160,000 |
| Materials stored on site | $8,000 |
| Total completed and stored | $168,000 |
| Less retainage at 10% | $16,800 |
| Total earned less retainage | $151,200 |
| Less previous certificates | $108,000 |
| Current payment due | $43,200 |
Over the whole job, $40,000 waits for the end, often months after the work it covers. The same job under a California private contract signed in 2026 could hold at most 5%: $8,400 at this point and $20,000 over the job.
Which states cap retainage, and at what rate?
California, New York, Texas and Florida each have rules, in different shapes:
| State | Private jobs | Public jobs | Release |
|---|---|---|---|
| California | 5% of each payment and 5% of the contract price in total, for contracts signed from 1 January 2026 (Civil Code 8811); not on residential projects of four stories or fewer that aren't mixed-use | 5% (Public Contract Code 7201) | Owner pays within 45 days after completion (Civil Code 8812) |
| New York | 5% of the contract sum on projects of $150,000 or more (General Business Law 756, 756-c, 757) | Not covered by these sections | Within 30 days after final approval; 1% a month interest if late |
| Texas | The owner must reserve 10% until 30 days after completion, for lien claimants (Property Code 53.101); the contract's own retainage is separate | 10% under $5 million, 5% at $5 million or more (Government Code 2252.032) | As the contract says; payment requests are due within 35 days (Property Code 28.002) |
| Florida | As the contract says | 5% of each payment on contracts over $200,000 (Statutes 255.078) | Same time limits as any payment request |
For any other state, read that state's own statute for where the project is. In New York, a private contract clause asking for more than 5% is void under General Business Law 757.
What are the rules on federal jobs?
Federal contracting officers pay in full when progress is satisfactory and may hold back up to 10% only when it isn't (FAR 52.232-5). FAR 32.103 adds that retainage "should not be used as a substitute for good contract management". At substantial completion the officer keeps only what protects the Government and releases the rest; retained amounts are due as the contract says or, if it's silent, 30 days after the officer approves their release (FAR 52.232-27).
When must retainage be released?
When the contract says, and no later than the state's deadline. In California the owner must pay the retention within 45 days after the work is completed; in New York within 30 days after final approval of the work; on federal jobs within 30 days of the contracting officer approving release when the contract is silent. Release usually needs paperwork first: final lien waivers, closeout documents and a finished punch list.
Can the owner keep retainage for punch-list items or a dispute?
Only a limited amount. In California, if there is a good-faith dispute, the owner may withhold no more than 150% of the disputed amount from final payment. On the $400,000 job with $20,000 retained and $3,000 of punch-list work disputed, the owner may hold $4,500 and must pay the other $15,500 within 45 days of completion.
Can a GC hold more retainage from a sub than the owner holds from the GC?
Not in California or New York: a subcontract's retainage percentage can't exceed the one in the owner's contract with the GC. On federal jobs the prime contractor must pay subs for satisfactory work within 7 days of being paid (31 U.S.C. 3905), and the subcontract may permit retainage on the sub as agreed.
What happens if the owner pays late?
The owner owes interest or a penalty at the rate the state sets. In Texas an unpaid amount bears interest at 1.5% a month, so a $43,200 payment made a month late costs the owner $648. In California an owner who wrongfully withholds a progress payment owes 2% a month; in New York, retainage released late carries 1% a month.
Does retainage apply to stored materials?
Yes on a standard pay application: retainage is taken on the total completed and stored, so stored materials carry it too. Texas caps the rate on public jobs per line of the schedule of values, "including materials and equipment delivered on site to be installed".
How should a contractor track retainage?
Per job and per subcontractor, from the pay applications, never as one figure in the books:
- Retainage receivable is money you've billed and earned but can't collect yet. It sits inside "billed to date" on the WIP schedule; cash collected doesn't include it.
- Retainage payable is what you hold from each sub, released on the same terms once the owner pays you.
- Release dates: completion, final approval and the state's deadline, so a late release is chased with interest.
- Release paperwork: lien waivers, closeout documents and the punch list, tracked per job.
The construction demo's US build holds retainage on every pay application, on work completed and stored materials, at a rate set per application. It doesn't yet bill a retainage release or track retainage held from subcontractors; those are parts we'd build for a contractor.
Quoted from the official texts (30)
“If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full.”
FAR 52.232-5(e), retainage
“However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved.”
FAR 52.232-5(e), retainage
“shall release to the Contractor all the remaining withheld funds.”
FAR 52.232-5(e), retainage at substantial completion
“Retainage should not be used as a substitute for good contract management, and the contracting officer should not withhold funds without cause.”
FAR 32.103
“may be adjusted as the contract approaches completion to recognize better than expected performance”
FAR 32.103
“Upon completion of all contract requirements, retained amounts shall be paid promptly.”
FAR 32.103
“30 days after approval by the Contracting Officer for release to the Contractor.”
FAR 52.232-27, retained amounts
“a payment clause which obligates the prime contractor to pay the subcontractor for satisfactory performance under its subcontract within 7 days out of such amounts as are paid to the prime contractor by the agency under such contract”
31 U.S.C. 3905(b)(1), subcontract payment clause
“This section is applicable to a contract relating to a private work of improvement entered into on or after January 1, 2026.”
California Civil Code 8811(a)
“shall not exceed 5 percent of the payment.”
California Civil Code 8811(b)(1)(A)
“In no event shall the total retention proceeds withheld exceed 5 percent of the contract price.”
California Civil Code 8811(b)(1)(B)
“the percentage of the retention payment withheld shall not exceed the percentage specified in the contract between the owner and the direct contractor.”
California Civil Code 8811(b)(1)(C)
“Paragraph (1) does not apply to an owner, direct contractor, or subcontractor on a residential project if the project is not mixed-use and does not exceed four stories.”
California Civil Code 8811(b)(3)
“the owner shall, within 45 days after completion of the work of improvement, pay the retention to the contractor.”
California Civil Code 8812(a)
“the owner may withhold from final payment an amount not in excess of 150 percent of the disputed amount.”
California Civil Code 8812(c)
“An owner that violates this section is liable to the direct contractor for a penalty of 2 percent per month on the amount wrongfully withheld”
California Civil Code 8800(c)
“The retention proceeds withheld from any payment by a public entity from the original contractor, by the original contractor from any subcontractor, and by a subcontractor from any subcontractor thereunder shall not exceed 5 percent of the payment.”
California Public Contract Code 7201(b)(1)
“an owner may retain no more than five per centum of the contract sum as retainage.”
New York General Business Law 756-c
“in no case shall retainage exceed the actual percentage retained by the owner.”
New York General Business Law 756-c
“Retainage shall be released by the owner to the contractor no later than thirty days after the final approval of the work under a construction contract.”
New York General Business Law 756-c
“shall be subject to the payment of interest at the rate of one percent per month on the date retention was due and owing.”
New York General Business Law 756-c
“in an amount exceeding five percent of the contract sum.”
New York General Business Law 757(5)
“equals or exceeds one hundred fifty thousand dollars.”
New York General Business Law 756(1)
“for 30 days after the work under the contract is completed, the owner shall reserve:”
Texas Property Code 53.101(a)
“not later than the 35th day after the date the owner receives the request.”
Texas Property Code 28.002(a)
“An unpaid amount bears interest at the rate of 1-1/2 percent each month.”
Texas Property Code 28.004(b)
“if the total value of a public works contract is $5 million or more, a governmental entity may not withhold retainage in an amount that exceeds five percent of the contract price”
Texas Government Code 2252.032(b)(2)
“including materials and equipment delivered on site to be installed”
Texas Government Code 2252.032(b)(1)
“a public entity may withhold from each progress payment made to the contractor an amount not exceeding 5 percent of the payment as retainage.”
Florida Statutes 255.078(1)
“if the total cost of the construction services purchased as identified in the contract is $200,000 or less.”
Florida Statutes 255.078(6)
Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.
Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.
Official sources
- FAR 52.232-5, Payments Under Fixed-Price Construction Contracts. Acquisition.gov (General Services Administration), November 3, 2026.
- FAR 52.232-27, Prompt Payment for Construction Contracts. Acquisition.gov (General Services Administration), November 3, 2026.
- FAR 32.103, Progress payments under construction contracts. Acquisition.gov (General Services Administration), November 5, 2026.
- 31 U.S.C. 3905, Payment provisions relating to construction contracts. Legal Information Institute, Cornell Law School, November 5, 2026.
- California Civil Code 8800, 8811 and 8812. California Legislative Information, November 5, 2026.
- California Public Contract Code 7201. California Legislative Information, November 5, 2026.
- New York General Business Law 756, 756-c and 757. New York State Senate, November 5, 2026.
- Texas Property Code chapter 28 and section 53.101. Texas Legislature, November 5, 2026.
- Texas Government Code 2252.032. Texas Legislature, November 5, 2026.
- Florida Statutes 255.078, Public construction retainage. The Florida Legislature, November 5, 2026.
What this page is not
A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .
Talk to us about your systems.
Tell us what's held together with workarounds right now. We reply to every message ourselves.