RERA for builders: the 70% account, withdrawals and records

Under the Real Estate (Regulation and Development) Act, 2016, a promoter registers each project with the state RERA, deposits 70% of the money collected from buyers in a separate account for that project, withdraws it only in proportion to completion as certified by an engineer, an architect and a chartered accountant, has the account audited every year, and is liable for structural defects for five years after possession.

Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

A model of a residential tower beside a bank passbook and a stamped certificate: a RERA project account.

Which projects must be registered with RERA?

Real estate projects where plots, apartments or buildings are sold, above the size thresholds in the Act (generally land over 500 square metres or more than eight apartments, which states may lower). The promoter registers the project with the state's RERA authority before advertising or selling, and the registration carries the project's plans, approvals, schedule and the bank account below. States run their own portals and rules; check yours.

What is the 70% separate account?

Section 4(2)(l)(D) of the Act requires the promoter to deposit 70% of the amounts realised from buyers, from time to time, in a separate account in a scheduled bank, to be used only for the cost of land and construction of that project. Withdrawals must be in proportion to the percentage of completion, certified by an engineer, an architect and a practising chartered accountant, and the account is audited within six months of the end of each financial year, with the accountant verifying that the money was used for the project.

What must be updated during the project?

Quarterly updates on the RERA website: bookings, approvals received, and the status of construction against the schedule, in the format your state's rules set. Delays and changes to plans have their own rules, including buyer consent for changes to sanctioned plans in many cases.

What is the five-year defect liability?

Section 14(3) makes the promoter responsible for rectifying structural defects, workmanship, quality or services defects that buyers report within five years of handing over possession, at no charge, within 30 days. Builders usually carry this down to their contractors through retention and bank guarantees.

How does a RERA withdrawal work in practice?

A worked example, with made-up figures. A project's estimated cost is ₹40 crore (land ₹10 crore, construction ₹30 crore). By 31 December the promoter has collected ₹18 crore from buyers and deposited 70%, ₹12.6 crore, in the project's RERA account. The engineer certifies construction at 35% complete, the architect certifies the same stage, and the chartered accountant certifies the cost incurred: land ₹10 crore paid, construction ₹10.5 crore spent.

LineAmount (₹ crore)
Land cost incurred10.0
Construction cost incurred (35% of ₹30 crore)10.5
Total cost incurred20.5
Proportion of estimated cost incurred51.25%
Balance in the RERA account12.6

The promoter may withdraw against the certified cost incurred, in proportion to completion; here the account holds less than the certified cost, so the whole balance can be drawn against these certificates, and the rest of the cost was funded from the promoter's own money.

The certificates go with each withdrawal request to the bank, and the same figures appear in the annual audit. The weak point is the cost certificate: if site costs are in spreadsheets, the chartered accountant has to rebuild them every quarter. If costs are booked to the project as they happen, the certificate is a report.

What usually goes wrong?

  • Collections deposited late or short. Money received in a general account and transferred later breaks the trail; deposit the 70% as each payment is received.
  • Common costs not allocated. Head office, plant and shared staff costs used across projects need an allocation basis the accountant can certify; agree it at the start.
  • Cost to complete not updated. The estimate in the registration is a baseline; when it changes, the proportion of completion changes with it.
  • Quarterly updates missed. Most state portals show the last update publicly, and buyers check.
  • Contractor bills not tied to measured work. Progress certified by the engineer should match the running bills paid to contractors for the same period.

What are the penalties?

The Act sets them by contravention. Advertising or selling a project that should have been registered and wasn't can cost up to 10% of the estimated project cost (section 59); other contraventions by a promoter, up to 5% (section 61); and failing to comply with an order of the authority can lead to further penalties. Buyers can also claim interest for delayed possession. State authorities publish their orders, and buyers read them.

Does RERA apply to a contractor?

Not directly: RERA obligations sit with the promoter (the developer). A contractor building for a developer feels it through the contract: progress evidence for the engineer's certificate, quality records for the five-year defect liability, and retention or guarantees held against defects. A contractor whose bills, measurements and site records are in order makes the developer's certificates easier, which is a selling point when bidding.

What records make RERA compliance easier?

  • Collections per project and per buyer, with the 70% deposited and the date.
  • Costs per project, land and construction separately, so the percentage of completion and the withdrawal can be certified from the books, not estimated. See job cost per site.
  • Contractor bills certified against measured work, so progress is evidenced. See RA bills.
  • Labour cess paid per project; see labour cess.

Our construction demo keeps costs, running bills and site progress per project, which is the base a RERA withdrawal certificate is built from; the RERA account and quarterly reports are parts we would add. See software for construction companies.

Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.

Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.

Official sources

What this page is not

A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .

Talk to us about your systems.

Tell us what's held together with workarounds right now. We reply to every message ourselves.