Hydrostatic test

The pressure test of a finished boiler or vessel filled with water, held above its MAWP and inspected for leaks: at least 1.3 × MAWP (times a stress ratio) for an ASME Section VIII Division 1 vessel, 1.5 × MAWP for a Section I boiler.

Pujan Motiwala · · Updated

It is the last hold point before a stamped vessel or boiler ships: the Authorized Inspector witnesses it, and the test pressure goes on the data report. Getting it wrong is easy: the pressure is measured at the top, a gauge at the bottom reads higher by the water head, and the gauge's dial must be between 1.5 and 4 times the test pressure (UG-102).

A calculator, worked examples and the procedure are in the hydrostatic test guide. Under IBR in India the hydraulic test record goes with the registration documents.