Documents for boiler registration under IBR 2026

Under regulation 8 of IBR 2026, a boiler's registration application goes to the Chief Inspector with four sets of documents: the Inspecting Authority's certificate (Form I Part B or C), the maker's certificate (Form IV Part A), drawings, and the material certificates (Form V Part A, with the Form V Part B extract).

Pujan Motiwala · Checked against the Gazette on · IBR 2026, in force from 1 October 2026

Seven steps to register a boiler under IBR 2026: 1, submit the application with Form I Part B or C, Form IV Part A, drawings, and Form V Parts A and B; 2, the Inspector checks the boiler at site; 3, hydraulic test; 4, provisional order in Form X; 5, registry number engraved on the front plate within one month, for example GT above 1234; 6, steam test, entered in Form XI; 7, certificate for use in Form XII. Regulations 8, 300, 301 and 310.
The seven steps from application to certificate for use, under regulations 8, 300, 301 and 310 of IBR 2026.

Which documents go with a boiler registration application?

Regulation 8 of the Indian Boiler Regulations, 2026 lists what goes to the Chief Inspector with an application to register a boiler. They may be filed on paper or electronically with digital signatures.

  1. The Inspecting Authority's certificate: Form I Part B for a shop-assembled boiler, or Form I Part C for one assembled at site. Form I Part D replaces either when permitted variations apply.
  2. The maker's certificate of manufacture and test: Form IV Part A, signed by the maker.
  3. Drawings: for a shop-assembled boiler, drawings showing principal dimensions, sections, maker's number, stamp position, bill of material, welding details and design parameters.
  4. Material certificates: the steel maker's Form V Part A, and the Form V Part B extract of every material test certificate used.

What else is needed for some boilers?

Fusion-welded drums need a diagram of weld repairs and the heat-treatment temperature charts (regulation 8(d)(v)). Alloy steels used in the creep range in the furnace or superheater zone need two 1,000-hour stress rupture tests for each grade (regulation 8(d)(vi)). Boilers under 20 tons per hour carry all their mountings and fittings certificates; at 20 tons per hour and above, mountings for site-assembled boilers may be supplied separately (regulation 8(d)(vii)).

What happens after the application is filed?

Under regulation 300, the Inspector inspects the boiler at site for transit damage and checks the maker's certificate against the boiler. The Inspector then conducts the hydraulic test and issues a provisional order in Form X, so the boiler can be used while registration completes. The particulars and test results go into the Memorandum of Inspection Book, Form XI, which goes to the Chief Inspector with the maker's papers. Once the registry number is issued, the Inspector conducts a steam test and enters it in Form XI (regulation 300(4)); the certificate for use, Form XII, follows (regulation 310).

When is the registry number engraved?

Within one month of receiving it, the registry number is cut into the boiler's front plate or wherever the Inspector points out, and the engraving is reported to the Chief Inspector within the same month (regulation 301). The number sits below the state's letters, for example GT for Gujarat and MR for Maharashtra; a small industrial boiler's number carries an "S" prefix.

Quoted from the regulations (13)

“The engraving shall be complete and ready for verification within one month from the date of receipt of registry number, and the fact shall be reported to the Chief Inspector of Boiler within this period.”

IBR 2026, regulation 301(2)

“A certificate in Form-I(Part-B) or Form-I(Part-C), as the case may be, from an Inspecting Authority, certifying that the material was tested and the boiler was built under their supervision”

IBR 2026, regulation 8(a)(i)

“A certificate in Form-IV(Part-A) of manufacture and test signed by the maker of the boiler or its representative”

IBR 2026, regulation 8(b)

“In case of shop assembled boilers, drawings to an appropriate scale showing the principal dimensions, sections, maker’s number, position of Inspecting Authority’s stamp, bill of material, welding details and design parameters.”

IBR 2026, regulation 8(c)(i)

“A certificate in Form-V(Part-A) from the steel maker and a certificate from the maker of the plates or bars”

IBR 2026, regulation 8(d)(i)

“The extract of all test certificates of materials used in boiler and boiler components in Form-V(Part-B) along with Form-IV(Part-A).”

IBR 2026, regulation 8(d)(iv)

“In the case of fusion welded drums, diagram of weld repairs and temperature charts of heat-treatment shall also be furnished.”

IBR 2026, regulation 8(d)(v)

“Alloy steel materials used in creep range in furnace or super-heater zone”

IBR 2026, regulation 8(d)(vi)

“two numbers of 1000 hour stress rupture tests shall be carried out at 50°C above the maximum service temperature for each grade of alloy steel and Nickel alloys”

IBR 2026, regulation 8(d)(vi)(A)

“all boilers of capacity less than 20 tons per hour shall carry all the mountings or fittings certificates in respective forms”

IBR 2026, regulation 8(d)(vii)

“the Inspector shall conduct hydraulic test as per requirements of regulations 298 and a provisional order under section 14 in Form-X shall be issued after the hydraulic test.”

IBR 2026, regulation 300(2)

“after issue of registry number, the Inspector shall conduct steam test as per regulation 299 and enter the details of steam test in Form-XI.”

IBR 2026, regulation 300(4)

“The registry number of every boiler shall, within a period of one month from the date of receipt thereof, shall be cut in the front plate”

IBR 2026, regulation 301(1)(a)(i)

See a boiler's IBR folder produced from its material certificates, with a sample company.

Free. Resets every night.

Built for a boiler manufacturer: ERP for boiler manufacturers · how the folder is produced

Official sources

What this page is not

A guide written by Ahrom Labs from the Gazette text; not legal advice. The Gazette governs wherever this page differs from it, and a state's Chief Inspector of Boilers may set procedures of their own. Last updated .