WPS vs PQR vs WPQ: what each proves and how they link

A PQR records a test weld: the actual materials, settings and test results that prove a procedure makes sound welds. A WPS is the instruction a welder follows, written with ranges the PQR supports. A WPQ records that one welder passed their own test. In ASME Section IX the PQR comes first, the WPS cites it, and each welder needs a WPQ.

Pujan Motiwala · Written to the ASME BPVC 2025 Edition · checked against ASME's and the National Board's public pages on

Three document sheets on a clipboard with a welding electrode and a welded test coupon on top: the WPS, PQR and WPQ.
Video chapters (10)
  1. 0:00WPS vs. PQR vs. WPQ Overview (ASME Section IX)
  2. 0:22How Every Code Weld Traces Back: The 5-Link Inspector Audit Chain
  3. 0:46Document Roles Compared: PQR (QW-483), WPS (QW-482) & WPQ (QW-484A/B)
  4. 1:046-Step Shop Sequence & Table QW-451 Tension/Bend Coupon Tests
  5. 1:26Essential vs. Nonessential Changes, Multi-PQR WPSs & Ownership
  6. 1:46Why AWS D1.1 Fails ASME Audits + Article V SWPS (QW-485) & Free Forms
  7. 2:085 Official Free ASME Suggested Formats (QW-482 to QW-485 & QW-500)
  8. 2:28Linking Weld Maps, WPS, PQR, P-Numbers & QW-322 in Boiler ERP
  9. 2:462025 Edition Notice & Authorized Inspector Verification
  10. 3:00Next Steps: Essential Variables (S35), Positions (S36) & Continuity (S04)

What is the difference between a WPS and a PQR?

A PQR is the record of a test weld that proves a procedure works; a WPS is the instruction written from it. The PQR records what was actually used on one coupon (materials, filler, settings, preheat, heat treatment) and the test results; the WPS gives the welder a range for each variable, within what the PQR supports. A PQR is never edited to fit a job: if a job needs something the PQR doesn't support, a new coupon is welded.

PQRWPSWPQ
Full nameProcedure Qualification RecordWelding Procedure SpecificationWelder (or Welding Operator) Performance Qualification
ProvesThe procedure makes welds with the required strength and ductilityNothing by itself; it's the instructionThis person can make a sound weld
RecordsWhat was used on one test coupon, and the test resultsRanges for every variable, within what the PQR(s) supportThe welder's test, results and what they're qualified for
WrittenOnce per testFrom one or more PQRsOnce per welder per test
ASME's suggested formQW-483QW-482QW-484A (welder), QW-484B (operator)

What is a WPQ?

A WPQ is the record that one welder (or welding operator) passed a performance test, and of the process, positions, thicknesses, diameters and filler it qualifies them for. It belongs to the person, not the procedure: a welder qualified on one WPS may weld to other WPSs within their qualified ranges. What a test covers is in welder qualification.

In what order does a shop build them?

  1. Draft a WPS for the job (often called a pWPS until it's qualified).
  2. Weld a test coupon to it and record every variable actually used.
  3. Test the coupon. For a groove-weld procedure, Section IX requires tension tests for strength and guided bend tests for ductility (QW-451 sets how many; side bends replace face and root bends on thicker coupons). Toughness tests are added when the construction code requires impact testing.
  4. Write the PQR from the coupon record and the test results, and certify it.
  5. Issue the WPS, citing the PQR, with each variable's range set by what the PQR qualifies.
  6. Qualify each welder and record it on a WPQ.

What tests does a PQR need?

For a groove weld, tension tests and guided bend tests cut from the coupon, in the numbers Section IX's QW-451 tables give for the coupon's thickness; for fillet welds, fillet weld tests. Charpy impact tests are added when the construction code requires toughness, which also brings in Section IX's supplementary essential variables. The results go on the PQR with the laboratory's report.

Which changes need a new PQR?

Every variable in Section IX is classified. Change an essential variable beyond what the PQR covers (base metal P-number, filler F-number, thickness range, post-weld heat treatment and others) and you need a new PQR; change a nonessential one and you only revise the WPS. See essential variables.

Can one WPS cite more than one PQR?

Yes, as long as every essential variable on the WPS is covered by at least one of the PQRs: for example, two PQRs that between them cover a wider thickness range. A PQR register with each PQR's qualified ranges worked out once prevents most WPS errors, which are usually ranges copied wrong.

Who signs the WPS and PQR?

The manufacturer or contractor that did the qualification certifies the PQR, and issues the WPS. The organization is responsible for its own qualifications, so a shop can't use another company's PQR. The Authorized Inspector reviews them before the procedure is used on Code work.

Can I use an AWS prequalified WPS on ASME work?

Not an AWS D1.1 prequalified procedure: ASME work needs Section IX qualification. Section IX does accept AWS's standard welding procedure specifications (SWPSs) listed in its Article V (QW-500), after the shop demonstrates one with a test weld, recorded on ASME's QW-485 format.

Where do I get the forms?

ASME publishes the suggested formats free on its data report forms page: QW-482 (WPS), QW-483 (PQR), QW-484A (welder WPQ), QW-484B (welding operator) and QW-485 (SWPS demonstration). A shop may use its own layout if it records everything Section IX requires.

How does a weld trace back through all three?

On a job's file, any weld should trace like this: weld number on the weld map → the welder's stamp → that welder's WPQ and continuity → the WPS used → the PQR behind it → the filler metal's certificate and the base metal's MTR by heat number. An Authorized Inspector will pick a weld and walk it, and when the links live in different binders this is where audits stall.

What does our software keep for it?

Our US boiler demo keeps those links per job and prints them in the ASME record package: the weld map lists each seam's joint category and type, WPS, welder stamps and NDE report; the welding page lists each WPS with its PQR, P-numbers, thickness range and PWHT basis; welder continuity under QW-322 sits next to it. It records procedures the shop has qualified; it doesn't write or qualify them. See ERP for boiler and pressure vessel shops.

Quoted from the official text (5)

“Suggested Format for Welding Procedure Specifications (WPS)”

ASME Data Report Forms, QW-482

“Suggested Format for Procedure Qualification Records (PQR)”

ASME Data Report Forms, QW-483

“Suggested Format A for Welder Performance Qualifications (WPQ)”

ASME Data Report Forms, QW-484A

“Suggested Format B for Welding Operator Performance Qualifications (WOPQ)”

ASME Data Report Forms, QW-484B

“Suggested Format for Demonstration of Standard Welding Procedure Specifications (SWPS)”

ASME Data Report Forms, QW-485

WPS and PQR registers, welder continuity, heat numbers from receipt to nameplate, and the data report package: the records a Code shop keeps, in one system.

A boiler manufacturer's system, from enquiry to dispatch and the IBR folder, with sample logins: try the live demo.

A boiler and pressure vessel shop's system, from inquiry to shipping and the ASME data report package, with sample logins: try the live demo. Fixed price, scope agreed before work starts: see the prices.

What this page is not

A guide written by Ahrom Labs, not engineering advice, and not yet reviewed by an Authorized Inspector. The ASME Code is copyrighted and sold by ASME: paragraphs are cited by number and explained in our own words, never reproduced. Check every figure against your copy of the 2025 Edition and with your Authorized Inspector before relying on it. Last updated .