Interior design quotation format: what to include
An interior quotation should carry the BOQ (every item with its specification, unit, quantity, rate and amount, room by room), the design fee and how it is charged, GST shown separately, a payment schedule tied to stages, what is excluded, the validity of the rates, the timeline, and how changes will be priced. A quotation that is only a lump sum per room is where most disputes start.
Pujan Motiwala · Standards checked against the BIS catalogue on

What should an interior quotation include?
Everything the client needs to compare it and everything you need to bill it without an argument:
| Part | What it says |
|---|---|
| Header | Firm, GSTIN, client, site address, quotation number, date and revision |
| Scope summary | Rooms and trades covered, drawings or design version it is based on |
| BOQ | Each item by room: description with materials and brands, unit, quantity, rate, amount |
| Design fee | Percentage, per square foot or lump sum, and what it covers |
| Taxes | GST on each part at its rate, shown separately from the amounts |
| Payment schedule | Stages and the percentage due at each, see below |
| Exclusions | What is not included: civil changes, appliances, loose furniture, lights, society charges |
| Validity | How long the rates hold, often 15 to 30 days, because material prices move |
| Timeline | Start, key stages, handover, and what the client must do (approvals, site access) |
| Changes | How additions and substitutions are priced and approved, see variation orders |
| Warranty | Period and what it covers, by trade or brand |
| Signatures | Acceptance by the client, with the date |
How should the BOQ part be laid out?
Room by room, trade by trade inside each room, with the same item described the same way every time: "Wardrobe carcass in 18 mm BWP plywood with 1 mm laminate outside, 0.8 mm inside, soft-close hinges, brand X" rather than "Wardrobe". Give the unit (sq ft of shutter area, running ft, number) and the measurement rule. See how to make an interior BOQ, the measurement rules and the free BOQ template.
How is the design fee shown?
As its own section, separate from execution: a percentage of the project cost (and of which cost), a rate per square foot of carpet area, or a lump sum by stage (concept, drawings, site supervision). Say how many design revisions are included and what a further revision costs.
What payment schedule is usual?
Stage-wise, with each stage something the client can see. A common pattern for a turnkey project:
| Stage | Share |
|---|---|
| Booking, on signing | 10% |
| Design approved, before material is ordered | 40% |
| Carcass and civil work complete | 30% |
| Finishing complete, before handover | 15% |
| After handover and snag list closed | 5% |
Large contracts borrow the public works model: CPWD's contract allows mobilization advance with conditions, "Mobilization advances not exceeding 10% of the tendered amount may be given, if requested by the contractor in writing", and holds a security deposit that "shall be collected from the running bills and the final bill of the contractor". On a residential project the last 5% does the same job: it is released after the snag list is closed.
How should GST be shown?
Separately, on each part at its rate, with the totals before and after tax. Design services and the execution of interior work may attract GST differently depending on how the contract is structured (a works contract for the whole job, or separate supplies), so confirm the treatment with your CA before you fix the format.
What causes disputes after a quotation is accepted?
- Lump sums per room with no item list, so nobody can say what was included.
- Brands and thicknesses not written, so a cheaper board is a "substitution" only after the fact.
- No measurement rule, so the final bill's areas don't match the quote's.
- Changes agreed on the phone with no price, settled at the last payment.
- Validity not stated, so a quote accepted four months later is expected at the old rates.
Is there a free interior quotation format to download?
Yes: a quotation as Excel, Word, PDF, free under CC BY 4.0. It has the room-by-room lines with specifications, the design fee, GST shown separately and the stage-wise payment schedule above, with the percentages as typed cells. The sample lines and rates are made up; replace them with your own.
How can a quotation be built faster?
From an item library: each item with its description, unit and current rate, picked into rooms, so the quotation, the BOQ and later the bills use the same lines. Our interior design system for Savistar & Saag builds quotations this way, with stages that turn into invoices. See software for interior design firms and ERP for interior design firms.
Quoted from the official text (2)
“Mobilization advances not exceeding 10% of the tendered amount may be given, if requested by the contractor in writing within six months of the order to commence the work.”
CPWD General Conditions of Contract (April 2026), clause 10B
“The security deposit shall be collected from the running bills and the final bill of the contractor”
CPWD General Conditions of Contract (April 2026), clause 1A
Paste a BOQ from Excel and see what each line leaves open, then print it as a quotation.
Designer Ops keeps your own BOQ library and every quote, turns an accepted quote's payment stages into invoices, then runs the project: orders, site visits and the workshop. Try the live demo · system for interior designers · what to require from one
Official sources
- Indian Standards catalogue (Know Your Standards). Bureau of Indian Standards, October 23, 2026.
- General Conditions of Contract, Construction Works, April 2026 (copy hosted by IIT Hyderabad). Central Public Works Department, April 1, 2026.
What this page is not
A guide written by Ahrom Labs; not legal, tax or engineering advice. Indian Standards are cited by number and title from the BIS catalogue, not quoted; the standard governs wherever this page differs from it. No rates are given: they change with city and month. Last updated .