GST on works contracts: rate, ITC and GST TDS
Under GST, a works contract is a contract for building, construction, repair or similar work on immovable property where goods pass to the client in the course of the work. It is a supply of services, taxed as one composite service on the whole value, generally at 18% (9% CGST + 9% SGST) where the property is. Government clients deduct GST TDS (1% CGST + 1% SGST) on contracts over ₹2.5 lakh, and input tax credit is blocked for building your own premises.
Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

What is a works contract under GST?
A works contract is a contract for building, construction, fabrication, completion, erection, installation, fitting out, improvement, modification, repair, maintenance, renovation, alteration or commissioning of any immovable property, where property in goods passes in the course of the work (section 2(119) of the CGST Act, 2017). The GST Council's note stresses the limit: only work on immovable property qualifies. Painting a car or fabricating a machine with your own material is a composite supply, but not a works contract.
Is a works contract a supply of goods or of services?
Of services. Schedule II, paragraph 6(a) of the CGST Act treats a works contract as a supply of services, so the whole contract value, materials included, is taxed as one service, not split into goods and labour as it was under VAT and service tax.
What is the GST rate on a works contract?
Generally 18%: 9% CGST plus 9% SGST (or 18% IGST), with lower rates only for the works a rate notification names. The rates are in serial number 3 of Notification 11/2017-Central Tax (Rate), as amended. The GST Council's 2017 note listed the general entry at 9% + 9% and lower entries at 6% + 6% for works such as roads and bridges for public use, low-cost housing and some government works. Those lower entries have been changed several times since; from 22 September 2025, Notification 15/2025-Central Tax (Rate) moved items (vii), (viii) and (x) of serial 3 to 9% CGST. Take the rate for your contract from the notification as it stands on the date of supply, or from your tax adviser, not from an old article.
Can the client claim input tax credit on my bill?
Not when the client uses your works contract to build its own immovable property, such as an office or a factory shed: section 17(5)(c) blocks that credit, except for plant and machinery. A main contractor that buys a subcontractor's works contract to supply its own works contract can take the credit.
| Who receives the works contract service | Input tax credit |
|---|---|
| A business building its own office, factory shed or other immovable property | Blocked (section 17(5)(c)) |
| The same, for plant and machinery | Allowed: plant and machinery is excluded from the block |
| A main contractor buying a subcontractor's works contract to supply its own works contract | Allowed |
Can a contractor claim ITC on cement, steel and other inputs?
Yes, when they go into a works contract you supply to a client: you charge GST on that supply and set the credit against it. Section 17(5)(d) blocks credit only for goods and services used to construct immovable property on your own account, such as your own office or godown (other than plant or machinery).
What is GST TDS, and when does the client deduct it?
Tax deducted at source under section 51 of the CGST Act: government departments, local authorities, government agencies and other notified persons deduct 1% CGST plus 1% SGST from payments for a contract whose taxable value exceeds ₹2.5 lakh. It's worked out on the value excluding GST, and the deductor pays it to the government within ten days after the end of the month. It isn't deducted when the supplier's location and the place of supply are in a state other than the one where the recipient is registered. It is separate from income-tax TDS; both can come off the same bill.
On a ₹18,50,000 RA bill to a state department, GST TDS is ₹18,500 CGST plus ₹18,500 SGST: ₹37,000.
Which state's GST applies to a works contract?
The state where the property is. The GST Council's note says the place of supply "would be where the immovable property is located" when supplier and recipient are both in India. So a Gujarat contractor working on a site in Maharashtra charges IGST to a client registered in Gujarat; CGST plus SGST apply where the contractor and the site are in the same state.
When is GST due on an RA bill?
At the time of supply: for services, the earlier of the invoice date (if the invoice is issued in time) and the date payment is received (section 13). Each running account bill is a supply, so the contractor issues a tax invoice for the bill's value with GST on top.
| Line | ₹ |
|---|---|
| Gross value of RA bill #3 | 18,50,000 |
| CGST 9% | 1,66,500 |
| SGST 9% | 1,66,500 |
| Invoice value | 21,83,000 |
The figures are made up.
Is GST payable on a mobilisation advance or on security deposit?
Ask your adviser before you decide. For services, receiving a payment can fix the time of supply, but whether an interest-bearing mobilisation advance is a payment for the supply is argued both ways. Security deposit is deducted from a bill whose full value has already been invoiced; how a deposit that is later forfeited is taxed is a separate question, and practitioners disagree on it.
What should a contractor's system do for GST?
- Classify each contract as a works contract or not, with the place of supply (where the property is).
- Issue a GST invoice for each RA bill from the measured value.
- Keep input tax credit apart where it is blocked (your own buildings) and where it is allowed.
- Record the GST TDS each government client deducts against the bill it belongs to.
- Reconcile GST invoices with RA bills and payments, so nothing is billed or credited twice.
In the construction demo, RA bills and trading invoices carry HSN or SAC codes and the CGST and SGST or IGST split, and the month's GST checklist shows output tax and the GSTR-1 summary by customer and HSN, with what's missing and the due dates. It doesn't yet record GST TDS deducted by clients or tag input tax credit as blocked or allowed; those are parts we'd build.
Quoted from the official texts (13)
““works contract” means a contract for building, construction, fabrication, completion, erection, installation, fitting out, improvement, modification, repair, maintenance, renovation, alteration or commissioning of any immovable property wherein transfer of property in goods (whether as goods or in some other form) is involved in the execution of such contract.”
CGST Act, 2017, section 2(119), as quoted by the GST Council
“the term works contract has been restricted to contract for building construction, fabrication etc of any immovable property only.”
GST Council, Works Contracts in GST
“works contracts as defined in section 2(119) of the CGST Act, 2017 shall be treated as”
CGST Act, 2017, Schedule II, paragraph 6(a), as quoted by the GST Council
“input tax credit shall not be available in respect of the works contract services when supplied for construction of an immovable property (other than plant and machinery) except where it is an input service for further supply of works contract service.”
CGST Act, 2017, section 17(5)(c), as explained by the GST Council
“The rate of GST for Works Contract service has been prescribed in serial number 3 of Notification No. 11/2017-Central Tax (Rate)”
GST Council, Works Contracts in GST (rate)
“The place of supply would be where the immovable property is located.”
GST Council, Works Contracts in GST (place of supply)
“goods or services or both received by a taxable person for construction of an immovable property (other than plant or machinery) on his own account including when such goods or services or both are used in the course or furtherance of business.”
CGST Act, 2017, section 17(5)(d)
“to deduct tax at the rate of one per cent. from the payment made or credited to the supplier”
CGST Act, 2017, section 51(1)
“where the total value of such supply, under a contract, exceeds two lakh and fifty thousand rupees:”
CGST Act, 2017, section 51(1)
“the value of supply shall be taken as the amount excluding the central tax, State tax, Union territory tax, integrated tax and cess indicated in the invoice.”
CGST Act, 2017, section 51(1), Explanation
“the date of issue of invoice by the supplier, if the invoice is issued within the period prescribed under”
CGST Act, 2017, section 13(2)(a)
“with effect from the 22nd day of September, 2025”
Notification No. 15/2025-Central Tax (Rate)
“against item (vii), for the entry in column (4), the entry “9” shall be substituted;”
Notification No. 15/2025-Central Tax (Rate), serial number 3
Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.
Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.
Official sources
- Works Contracts in GST. GST Council (Directorate General of Taxpayer Services, CBEC), July 1, 2017.
- Central Goods and Services Tax Act, 2017 (as updated to 30.09.2020). Central Board of Indirect Taxes and Customs, September 30, 2020.
- Notification No. 15/2025-Central Tax (Rate), 17 September 2025 (G.S.R. 663(E)). Ministry of Finance, Gazette of India (copy hosted by the Bombay Chartered Accountants' Society), September 17, 2025.
What this page is not
A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .
Talk to us about your systems.
Tell us what's held together with workarounds right now. We reply to every message ourselves.