Job cost and margin per site for construction contractors

Add up every cost that belongs to the site (material used, site labour, plant and machines, site cash and subcontractors) and set it against the value of work done to date: the difference is the margin so far. Divide cost to date by progress to project the final cost, and compare it with the estimate. ICAI's AS 7 defines which costs belong to a contract, and says a loss expected on a contract is recognised at once, not when the job ends.

Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

Three small site models on a board, each with its own stack of coins and a blank tag: job cost and margin per site.

What is job cost per site?

It's the total of every cost that belongs to one site or contract, kept separately from every other site. A contractor running several sites at once can be profitable overall while one site loses money; job cost per site shows which one, while there's still time to act. It also tells you whether the estimate you bid was right, which is what the next bid depends on.

Which costs belong to a construction contract?

ICAI's Accounting Standard 7 (Construction Contracts) says contract costs comprise costs that relate directly to the contract, costs attributable to contract activity in general that can be allocated to it, and other costs the contract makes chargeable to the customer. Direct costs include:

  • Site labour, including site supervision.
  • Materials used in construction.
  • Depreciation of plant and equipment used on the contract, and hire of plant and equipment.
  • Moving plant, equipment and materials to and from the site.
  • Design and technical assistance directly related to the contract.
  • Estimated rectification and guarantee work, including expected warranty costs, and claims from third parties.

Which costs should not be charged to a site?

General administration costs the contract doesn't reimburse, selling costs, research and development the contract doesn't pay for, and depreciation of idle plant and equipment not used on that contract, under AS 7. Head office rent and salaries stay in the company's overheads; an idle mixer in the godown isn't a cost of the site it isn't on.

How do you work out the margin so far on a site?

Subtract cost to date from the value of work done to date. The value of work is the approved quantity of each BOQ item times its rate, not what has been billed or received: AS 7 notes that progress payments and advances may not reflect the work performed.

A made-up site with a contract value of ₹40,00,000 and an estimated cost of ₹28,00,000:

₹
Value of approved work to date (60% of the contract)24,00,000
Material used on site9,60,000
Site labour, from attendance and wages6,40,000
Site cash (kharchi) spent1,20,000
Machine days on site80,000
Cost to date18,00,000
Margin to date6,00,000 (25%)

How do you project a site's final cost?

Divide cost to date by progress, so the rest of the job is assumed to cost at the same rate. The site above is 60% done for ₹18,00,000, so it projects to ₹30,00,000 against an estimate of ₹28,00,000: a projected margin of ₹10,00,000 instead of the ₹12,00,000 planned, and ₹2,00,000 over budget. The projection is rough early in a job, so wait until some of the work is done (the demo waits for 5%) and check it against a fresh estimate to complete.

How do you know when a site is losing money?

When its projected cost is above its contract value, or its margin to date has turned negative. AS 7 is strict about it: when it's probable that total contract costs will exceed total contract revenue, the expected loss is recognised as an expense immediately, whatever stage the work is at. A site that is merely over its estimate is over budget; one projected to cost more than it earns is losing money, and needs attention now.

How does percentage of completion relate to job cost?

AS 7 allows the stage of completion to be measured by the cost incurred for work done against the estimated total cost, by surveys of work performed, or by the physical proportion of the work completed. A contractor that measures progress by approved BOQ quantities is using the physical method; the cost-to-cost method needs a regular estimate to complete. Your accountant decides which applies in your accounts.

What records does job cost per site need?

One record per cost, tagged with its site at the moment it happens:

  • Material issued to each site, valued at its purchase rate, from the stores records.
  • Attendance per worker per site per day, and each worker's wage.
  • Site cash spends, with receipts, per site.
  • Machine days per site, with a day rate for owned machines.
  • Subcontractor bills against the site.
  • The approved quantity of each BOQ item, from daily reports or measurements, and the contract rates.

See material consumption against BOQ for the check that explains the material line, and RA bills for what's billed against the same work.

What does the construction demo do?

In the construction demo, the director dashboard shows each site's contract, work done (approved work at BOQ rates), billed, received, cost to date and margin. Cost to date is material used on site at its rate, labour from attendance and wages, site cash spent, and machine days at each machine's day rate. Margin to date is work done less cost; once 5% of the work is done, projected cost is cost to date divided by progress, and projected margin is the contract less that, set against the planned margin from the estimate. Sites are marked on track, over budget or losing money, and Datum AI answers "is the Bhatt site making money?" with the same figures. It doesn't add subcontractor bills or head office allocations to a site's cost, or take a fresh estimate to complete; those are parts we'd build.

Quoted from the official texts (11)

“costs that relate directly to the specific contract;”

AS 7, contract costs

“costs that are attributable to contract activity in general and can be allocated to the contract; and”

AS 7, contract costs

“site labour costs, including site supervision;”

AS 7, direct costs

“costs of materials used in construction;”

AS 7, direct costs

“costs of moving plant, equipment and materials to and from the contract site;”

AS 7, direct costs

“the estimated costs of rectification and guarantee work, including expected warranty costs;”

AS 7, direct costs

“general administration costs for which reimbursement is not specified in the contract;”

AS 7, costs excluded

“depreciation of idle plant and equipment that is not used on a particular contract.”

AS 7, costs excluded

“the proportion that contract costs incurred for work performed upto the reporting date bear to the estimated total contract costs; or”

AS 7, stage of completion

“Progress payments and advances received from customers may not necessarily reflect the work performed.”

AS 7, stage of completion

“When it is probable that total contract costs will exceed total contract revenue, the expected loss should be recognised as an expense immediately.”

AS 7, expected losses

Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.

Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.

Official sources

What this page is not

A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .

Talk to us about your systems.

Tell us what's held together with workarounds right now. We reply to every message ourselves.