Rate analysis for construction items: CPWD method with example
Rate analysis builds the rate of one unit of an item (a cubic metre of concrete, a square metre of plaster) from the materials, labour, and tools and plant it takes, plus water charges and the contractor's overheads and profit. CPWD's Schedule of Rates and Analysis of Rates are the usual reference, and items not in the schedule are analysed from market rates.
Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

What is rate analysis?
Rate analysis works out the cost of one unit of an item of work from what goes into it: the quantity of each material, the labour by trade, tools and plant, then water charges and the contractor's overheads and profit. The result is the rate a contractor quotes against a BOQ line and the rate an owner checks it against.
What goes into a rate?
| Component | What it covers |
|---|---|
| Materials | Quantity per unit (with wastage) × rate delivered to site |
| Labour | Mason, helper, carpenter, bar bender and so on, in man-days per unit × wage |
| Tools and plant (T&P) | Mixers, vibrators, scaffolding, shuttering hire and wear, as a lump sum or per unit |
| Sundries | Small items not worth measuring |
| Water charges | Commonly 1% of the cost, in CPWD-style analyses |
| Overheads and profit | Commonly 15% of the cost, in CPWD-style analyses |
The analysis is usually for a round quantity (10 m³ of concrete, 10 m² of plaster) and divided down to the unit.
Can you show a worked example?
An illustrative analysis for 1 m³ of M20 nominal mix concrete (1:1.5:3) for a slab, excluding reinforcement and shuttering. Quantities and rates are examples, not CPWD's figures: use your own and the current schedule.
| Item | Quantity | Rate (₹) | Amount (₹) |
|---|---|---|---|
| Cement | 8.0 bags | 400 per bag | 3,200 |
| Coarse sand | 0.44 m³ | 2,800 per m³ | 1,232 |
| Stone aggregate 20 mm | 0.88 m³ | 2,200 per m³ | 1,936 |
| Mason | 0.17 day | 1,000 | 170 |
| Beldar (helper) | 2.0 days | 750 | 1,500 |
| Mixer and vibrator hire, fuel | 300 | ||
| Cost of materials, labour and T&P | 8,338 | ||
| Water charges at 1% | 83 | ||
| Overheads and profit at 15% | 1,251 | ||
| Rate per m³ | 9,672 |
Change any input and the rate changes with it, which is why the analysis, not just the rate, should be kept with the estimate.
What are CPWD's Schedule of Rates and cost index?
CPWD issues a Schedule of Rates (the Delhi Schedule of Rates, DSR) for standard items and revises it periodically: "The SORs are ordinarily revised once in two years." Between revisions, a cost index adjusts the schedule for price movement; the Works Manual defines it as "An indicator of the average cost movement over time of a fixed basket of representative goods and services related to execution of works" and says "The cost index shall be issued as on 1st April and 1st October every year." A CPWD detailed estimate is "based on the rates given in theSOR for those items covered by it and on market rates for the remaining items".
How are items not in the schedule rated?
From a market rate analysis: current quotations for the materials, local wages, and the same overheads and profit, with the quotations kept as evidence. CPWD's item-rate tender form is used where "most of the items are non-scheduled or specialized items and detailed analysis of rates is not available". The same applies to extra items and substitutions during the job: price them by analysis and get the rate agreed before the work, or it becomes a dispute at the final bill. See RA bills and the price escalation clause.
What wastage allowances are used?
Rate analyses add wastage to material quantities: typically a few percent for cement and steel and more for bricks and tiles, depending on the item and handling. CPWD's contract sets allowances for comparing theoretical with actual consumption of key materials; see material consumption vs BOQ. Use your own site history where you have it: a rate that assumes 2% wastage on a site that loses 6% is wrong by the difference.
How do you analyse a rate for plastering?
A second illustrative example: 10 m² of 12 mm cement plaster 1:6 on brick walls. Quantities and rates are examples.
| Item | Quantity | Rate (₹) | Amount (₹) |
|---|---|---|---|
| Cement mortar 1:6, wet volume 0.12 m³, about 0.15 m³ dry with wastage: cement | 0.62 bag | 400 | 248 |
| Sand | 0.13 m³ | 2,800 | 364 |
| Mason | 0.8 day | 1,000 | 800 |
| Beldar | 1.0 day | 750 | 750 |
| Scaffolding and sundries | 60 | ||
| Cost | 2,222 | ||
| Water at 1% | 22 | ||
| Overheads and profit at 15% | 333 | ||
| Rate per 10 m² | 2,577 | ||
| Rate per m² | 258 |
The labour figures drive most plaster rates; a site where masons do 15 m² a day instead of 12.5 is cheaper by the difference, which is why productivity belongs in the analysis rather than a single blended rate.
When does a contractor need its own rate analysis?
- Tendering on an item rate contract, to know which rates are low and which carry the margin.
- Pricing extra and substituted items during the job, with the analysis attached to the claim.
- Checking a subcontractor's quote for a trade.
- Escalation claims, where the price of a material in the analysis moves; see the price escalation clause.
Keep the analysis in a sheet where the material and labour rates sit in one place and every item refers to them, so updating the price of cement updates every rate that uses it.
Is there a free rate analysis format?
Yes: a rate analysis sheet as Excel, Word, PDF, free under CC BY 4.0. The Excel file carries the concrete example above and reaches the same ₹9,672 per m³; the water and overheads percentages are typed cells, so set them to your contract or schedule of rates.
How does rate analysis connect to the site?
The analysis says how much cement, sand and steel each unit should take. Comparing it with what the site actually consumed for the measured work is how a contractor finds wastage and theft. See material consumption vs BOQ. In our construction demo each BOQ line can carry a norm (so much of one material per unit of work, the same quantities a rate analysis uses), and the site's Material tab compares expected use with what was actually issued, flagging anything more than 10% out. See software for construction companies.
Quoted from the official texts (5)
“Complete and comprehensive estimate of a work, based on the rates given in theSOR for those items covered by it and on market rates for the remaining items, supported by detailed drawings and specifications.”
CPWD Works Manual 2022, Definitions
“The SORs are ordinarily revised once in two years.”
CPWD Works Manual 2022, 3.1.1.9
“To update the SOR, the nomenclature with specifications, market rate list, and analysis of rates are to be periodically revised.”
CPWD Works Manual 2022, 3.1.1.9
“The cost index shall be issued as on 1st April and 1st October every year.”
CPWD Works Manual 2022, 3.1.1.9
“An indicator of the average cost movement over time of a fixed basket of representative goods and services related to execution of works.”
CPWD Works Manual 2022, Definitions
Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.
Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.
Official sources
- CPWD Works Manual 2022. Central Public Works Department, November 3, 2026.
What this page is not
A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .
Talk to us about your systems.
Tell us what's held together with workarounds right now. We reply to every message ourselves.