What is Form VIII?

Form VIII of the Indian Boiler Regulations, 2026 is the final inspection report for boiler components, prescribed under regulation 293.

Download Form VIII as a PDF: the form as notified, cut from the Gazette of India (No. 596, 1 October 2026) with nothing changed.

Who issues and signs Form VIII?

The maker of the boiler components, approved by the Competent Person.

What does Form VIII record?

  • Report number and date, the maker and the boiler number
  • For each item: product identification number, drawing number, description, quantity and the Competent Person's identification mark
  • Signatures of the maker's representative and the Competent Person

When is Form VIII filed, and with what?

Goes to site with the components; erection is based on it.

What changed for Form VIII from IBR 1950?

New in IBR 2026. Components erected on the basis of an approved Form VIII need no further ground inspection, manufacturing drawings or design calculations at site.

  • Form I Part A: Inspecting Authority's certificate of inspection during construction, boiler made to a foreign code for export (was Form II-A)
  • Form I Part B: Certificate of inspection for shop assembled boilers (was Form II(1))
  • Form I Part C: Certificate of inspection for site assembled boilers at maker's works (was Form II(2))
  • Form I Part D: Inspecting Authority's certificate of inspection during construction of boilers with permitted variations from standard conditions (was Form II-B)
  • Form I Part E: Inspecting Authority's certificate of inspection after completion of boiler erection at assembly site (was Form II-C)
Quoted from the regulations (2)

“The boiler components shall be erected at site based on the final inspection report as per Form-VIII approved by Competent Person”

IBR 2026, regulation 293(2)

“there is no need for any ground inspection or submission of any other document like manufacturing drawings, design calculations.”

IBR 2026, regulation 293(2)

One email when the regulation or a form changes. No newsletter; reply “stop” any time.

See a boiler's IBR folder produced from its material certificates, with a sample company.

Free. Resets every night.

Built for a boiler manufacturer: ERP for boiler manufacturers · how the folder is produced · other rules an ERP must meet

Official sources

What this page is not

A guide written by Ahrom Labs from the Gazette text; not legal advice. The Gazette governs wherever this page differs from it, and a state's Chief Inspector of Boilers may set procedures of their own. Last updated .

Talk to us about your systems.

Tell us what's held together with workarounds right now. We reply to every message ourselves.