Pressure vessel data book: what goes in the MDB
A manufacturer's data book (MDB, also data dossier, final documentation or turnover package) is the bound set of records shipped with a vessel or heat exchanger: the Manufacturer's Data Report, drawings and calculations, MTRs, weld map, WPS, PQR and welder qualifications, NDE, PWHT and hydro test records, NCRs and the signed ITP. The purchaser's specification sets what goes in and in what order; only the data report is a Code document.
Pujan Motiwala · Written to the ASME BPVC 2025 Edition · checked against ASME's and the National Board's public pages on

Video chapters (10)
- 0:00What a Pressure Vessel Data Book (MDB / MRB) Is
- 0:22ASME UG-120 Data Report Requirement vs. Purchaser MDB Spec
- 0:46All 15 Typical MDB Sections (Section VIII, Exchangers & Section I)
- 1:08Which of the 6 Shop Departments Owns Each Record (Why Books Slip)
- 1:28Preliminary vs. Final Revisions & Searchable Bookmarked PDF Rules
- 1:485-Step Live Workflow: Kickoff Template, Live Links & Open-NCR Gate
- 2:08Official Citations: ASME UG-120, Data Report Forms & NBBI Registration
- 2:30Job AB-1001 Live MDB: Nameplate Gate & SHA-256 Rev 1 PDF in ERP
- 2:482025 Edition Notice & Authorized Inspector Verification
- 3:00Next Steps: ASME B31.1 vs. B31.3 Piping (S43), Data Reports (S15) & NBBI (S22)
What is a manufacturer's data book?
A manufacturer's data book (MDB) is the complete set of quality records for one vessel, exchanger or boiler, bound in a set order with an index and handed to the purchaser at shipment. Purchasers call it many things: data book, manufacturer's record book (MRB), data dossier, final documentation, turnover package. It is where the owner, their inspector and later a repair shop look first to find out what the item is and how it was proved.
Does the ASME Code require a data book?
No. The Code requires the Manufacturer's Data Report (U-1, U-1A, P-2 and the rest), certified by the manufacturer and the Authorized Inspector, a copy for the user, and either keeping it for the period in UG-120 or registering it with the National Board, which "maintains permanent records of pressure-retaining items that are registered". Everything else in a data book is there because the purchase order or the purchaser's specification asks for it. That is why two customers' data books for the same vessel differ in content and order.
What goes in a data book?
A typical order for a Section VIII vessel or shell-and-tube exchanger. Use the purchaser's list when they give one:
| Section | Contents |
|---|---|
| Cover and index | Job, purchase order, tag numbers, revision; contents with page numbers |
| Data report | U-1 or U-1A (U-1 with U-5 for shell-and-tube exchangers), National Board registration where applicable |
| Nameplate | A photo or rubbing of the stamped nameplate |
| Drawings and calculations | As-built general arrangement and details; design calculations |
| Signed ITP | Every point with its sign-offs; see inspection and test plans |
| Material | MTRs for every pressure part, with a material traceability list by part and heat number |
| Welding | Weld map; WPS, PQR and welder qualifications for every weld; continuity |
| NDE | RT, UT, PT, MT reports with the examiners' qualifications |
| Heat treatment | PWHT charts and procedure, where done |
| Pressure test | Hydrostatic test report, chart, gauge calibration certificates |
| Other tests the order asks for | Hardness surveys, PMI, ferrite, impact tests, tube expansion or leak tests |
| Nonconformances | NCR log with each NCR and its disposition; see NCRs |
| Bought-out items | Certificates for flanges, fittings, bolting, gaskets, relief devices |
| Dimensional and final inspection | Final dimensional report, visual, coating and preservation |
| Release | Shipping release, packing list |
For a Section I boiler the data report is a P-2 or P-3, and the purchaser's list usually adds the safety valve certificates and trim.
Where does each record come from?
From every department, which is why data books are late. Material receipt has the MTRs; welding has the WPS, PQR and welder records; the NDE contractor sends reports; the heat treater sends charts; QC holds the ITP, the hydro test and the NCRs; engineering holds the calculations and drawings; purchasing has the bought-out certificates. A data book assembled after shipment means chasing all of them for records made weeks earlier.
What is a preliminary vs a final data book?
Many purchase orders ask for a preliminary data book for review before shipment and a final one after. The preliminary is marked as such on every page and lists what is still to come; the purchaser comments; the final incorporates the comments and the last records (nameplate, final inspection, release) and is issued as a numbered revision. Once a revision is sent it should never change: a correction is the next revision, with the old one kept.
What format should a data book be in?
One searchable PDF per item (or per purchase order line), with:
- a contents page whose page numbers match the PDF's page numbers;
- bookmarks for every section;
- continuous page numbering, including inside the appended MTRs and reports;
- a revision and status on the cover;
- scans that are legible at 100% zoom, with the heat numbers readable.
Some purchasers still ask for a paper copy too; the PDF is the record.
How do you build a data book as the job runs?
By deciding the contents before work starts and attaching each record to its line as it is made:
- Set up the purchaser's list as a template: sections, required lines, which are not applicable and why.
- Link every record to the job when it is made: MTRs at receipt, welds with their WPS and welder, NDE reports to the weld, the hydro report to the test.
- Show what is missing at any time, so gaps are chased while the people are still on the job.
- Refuse to release while a required line is missing or an NCR is open.
- On release, store the PDF and a fingerprint of it, so the revision sent can be proved unchanged later.
Our US boiler demo does this. Job AB-1001's data book fills 16 lines from the records already in the system, marks 8 not applicable with reasons and shows the nameplate missing, so Release is disabled and says why; once the nameplate is uploaded, the preview has a cover, contents with page numbers, bookmarks and a PRELIMINARY stamp, and Release stores revision 1 with its SHA-256 fingerprint. Templates are edited per customer. Try it at the live demo (sample data) or see ERP for boiler and pressure vessel shops. The data report in it is our own layout carrying the form's fields; file the official ASME form or use the National Board's EDT.
Quoted from the official text (2)
“NBBI maintains permanent records of pressure-retaining items that are registered by individual manufacturers who meet a set of requirements.”
National Board, Data Report Registration page
“Registration with NBBI indicates that a pressure-retaining item is constructed in accordance with the ASME Boiler and Pressure Vessel Code (ASME Code) and is inspected by a qualified NBBI Commissioned Inspector.”
National Board, Data Report Registration page
WPS and PQR registers, welder continuity, heat numbers from receipt to nameplate, and the data report package: the records a Code shop keeps, in one system.
A boiler manufacturer's system, from enquiry to dispatch and the IBR folder, with sample logins: try the live demo.
A boiler and pressure vessel shop's system, from inquiry to shipping and the ASME data report package, with sample logins: try the live demo. Fixed price, scope agreed before work starts: see the prices.
Official sources
- Boiler and Pressure Vessel Certification. ASME, November 1, 2026.
- 2025 ASME Boiler and Pressure Vessel Code (Section VIII, Division 1, UG-120). ASME, July 1, 2025.
- ASME Data Report Forms. ASME, November 5, 2026.
- Data Report Registration. The National Board of Boiler and Pressure Vessel Inspectors, November 5, 2026.
What this page is not
A guide written by Ahrom Labs, not engineering advice, and not yet reviewed by an Authorized Inspector. The ASME Code is copyrighted and sold by ASME: paragraphs are cited by number and explained in our own words, never reproduced. Check every figure against your copy of the 2025 Edition and with your Authorized Inspector before relying on it. Last updated .