Nonconformance reports (NCR) in an ASME fabrication shop
A nonconformance report (NCR) records anything that doesn't meet the Code, the drawing or the purchase order: a failed weld, wrong material, a dimension out of tolerance. It holds the item, then records the disposition (repair, rework, use as is, reject), who approved it, the repair, the re-inspection and the close. For a Code item, use as is is only possible when the item still meets the Code.
Pujan Motiwala · Written to the ASME BPVC 2025 Edition · checked against ASME's and the National Board's public pages on

Video chapters (10)
- 0:00What an ASME Nonconformance Report (NCR) Records (Appendix 10)
- 0:22Closed-Loop NCR Workflow & All 10 Required Fields
- 0:465 NCR Dispositions: Rework, Repair, Use As Is (Code Rule), Scrap & Return
- 1:05Weld Repair & Re-Examination: UW-51 Full RT vs. UW-52 Spot RT
- 1:28Written Approvals, Independent Closure & Free CC BY 4.0 NCR Form
- 1:48Pre-Stamp Shop NCR vs. In-Service NBIC Part 3 (R Stamp / Form R-1)
- 2:06Official Sources: NBIC Part 3, NB-66 Form R-1, Appendix 10, UW-51 & UW-52
- 2:28Enforcing NCR Holds & Repair WPS-103R (Job AB-1005) in Boiler ERP
- 2:482025 Edition Notice & Authorized Inspector Verification
- 3:00Next Steps: Hardness & PMI (S41), R Stamp (S23) & ITPs (S39)
What is a nonconformance report?
A nonconformance report (NCR) is the record of something that doesn't meet a requirement, from the moment it is found to the moment it is closed. In a pressure vessel shop the requirement is the Code, the drawing, the purchaser's specification or the shop's own procedure: an RT that shows porosity beyond the limit, plate with a heat number that doesn't match its MTR, a nozzle out of position, a hydro test gauge out of calibration.
The Code doesn't prescribe the form. It requires the shop's quality control system to have a way of correcting nonconformities that the Authorized Inspector agrees to (Section VIII Division 1, Mandatory Appendix 10), and the shop's quality control manual describes it.
What goes on an NCR?
| Field | Why |
|---|---|
| NCR number, job, part, weld or heat number | So the NCR can be found from the part and the part from the NCR |
| What was found, against which requirement | The drawing, Code paragraph or specification it fails |
| Who found it, when, at which ITP step | Ties the failure to the inspection record |
| Hold | The item is tagged and the steps that depend on it are stopped |
| Disposition | Repair, rework, use as is, reject or return to supplier, with the reason |
| Approval of the disposition | QC manager; the Inspector where the manual says so; the purchaser where their order says so |
| Repair procedure | E.g. the repair WPS and the welder |
| Re-inspection | The new result, by the same method and criteria |
| Verification and close | Who checked the repair was done as dispositioned, and when the NCR closed |
| Cause and corrective action | Why it happened, and what stops it happening again |
What are the NCR dispositions?
| Disposition | What it means | When it is allowed on a Code item |
|---|---|---|
| Rework | Make it conform to the original requirement (re-machine, re-fit) | Yes; re-inspect to the original criteria |
| Repair | Make it acceptable by an approved method that differs from the original, e.g. a weld repair | Yes, to a qualified procedure, re-examined |
| Use as is | Accept it unchanged | Only if it still meets the Code, e.g. a recalculation shows the thinner plate still meets the required thickness. A purchaser can waive their own specification, never the Code |
| Reject or scrap | Remove it from the job | Always |
| Return to supplier | Send bought material back | For material that fails receipt; the replacement needs its own MTR |
How is a failed weld repaired and re-examined?
Remove the defect, re-weld to a qualified WPS (often a separate repair WPS) by a welder qualified for it, and re-examine by the same method and acceptance criteria. For full radiography, Section VIII Division 1 requires unacceptable imperfections to be repaired and the repaired area radiographed again (UW-51). Spot radiography adds a step: when a spot fails, two more spots are taken in the same weld increment, and the results of those decide whether the increment is repaired or fully radiographed (UW-52). If the vessel was post-weld heat treated or already hydrotested, check whether the repair needs PWHT again and a new hydrostatic test; plan on both, and agree it with the Inspector.
Keep the failed result. The NCR, the first report and the re-examination report together show the Inspector what happened; overwriting the first result is the fastest way to lose an audit.
Is a repair before stamping the same as an R stamp repair?
No. A repair during construction, before the data report is certified and the item stamped, is part of building it to the Code and is handled through your own quality control system and NCR. Once a stamped item is in service, repairs and alterations fall under the National Board Inspection Code (NBIC), whose Part 3 provides guidance "to perform, verify, and document acceptable repairs or alterations to pressure-retaining items regardless of code of construction". That work is done by an organization holding the National Board's R certificate and is documented on Form R-1, the National Board's NB-66 Report of Repair (alterations use R-2). See National Board registration and the R stamp.
Who approves a disposition?
The shop's manual names who. Typically the QC manager approves the disposition and verifies the repair; engineering signs off a use-as-is with its calculation; the Authorized Inspector accepts dispositions affecting Code requirements; and the purchaser approves anything their order reserves, such as repairs to tube-to-tubesheet joints or any use-as-is. Write the approval on the NCR, with the name and date, not in an email.
When is an NCR closed?
When the item meets the requirement again and someone other than the person who did the repair has verified it: repair done as dispositioned, re-inspection passed, records attached. An NCR that is closed before the re-inspection passes is a gap an auditor will find. The ITP steps it held only open again after the close.
Is there a free NCR form?
Yes: a one-page nonconformance report as Word, PDF, free under CC BY 4.0. It carries the fields in the table above: the requirement, what was found, the disposition and its approvals, the repair procedure, re-inspection, and cause and corrective action. Put your own NCR numbering and approval rules from the quality manual on it.
What should NCR software do?
- Raise an NCR from the failed inspection itself, carrying the job, part, weld and heat number.
- Hold the steps that depend on the failed one, enforced by the server, and release them only when the NCR is closed and a later inspection has passed.
- Keep dispositions to the people allowed to make them, and record repair, re-inspection, verification and close as separate signed steps.
- Keep every attempt; never overwrite the failed one.
- Print the NCR log into the job's data book.
Our US boiler demo runs this loop: on job AB-1005 an RT failed on weld L1 and an NCR was raised; the QC head dispositions it as a repair to WPS-103R, Production records the repair, QC inspects again (RT pass), verifies and closes, and only then does the held step open. The failed RT stays on file. Try it at the live demo (sample data) or see ERP for boiler and pressure vessel shops. R-1 reports are not in it yet.
Quoted from the official text (3)
“This Part provides information and guidance to perform, verify, and document acceptable repairs or alterations to pressure-retaining items regardless of code of construction.”
National Board, NBIC page, Part 3
“The National Board offers the Certificate of Authorization and R symbol stamp for the repair and/or alteration of boilers, pressure vessels, and other pressure-retaining items.”
National Board, R Certificate of Authorization page
“NB-66, Report of Repair”
National Board, NBIC report forms page
WPS and PQR registers, welder continuity, heat numbers from receipt to nameplate, and the data report package: the records a Code shop keeps, in one system.
A boiler manufacturer's system, from enquiry to dispatch and the IBR folder, with sample logins: try the live demo.
A boiler and pressure vessel shop's system, from inquiry to shipping and the ASME data report package, with sample logins: try the live demo. Fixed price, scope agreed before work starts: see the prices.
Official sources
- Boiler and Pressure Vessel Certification. ASME, November 1, 2026.
- 2025 ASME Boiler and Pressure Vessel Code (Section VIII, Division 1, UW-51, UW-52 and Mandatory Appendix 10). ASME, July 1, 2025.
- National Board Inspection Code (NBIC). The National Board of Boiler and Pressure Vessel Inspectors, November 6, 2026.
- R Certificate of Authorization. The National Board of Boiler and Pressure Vessel Inspectors, November 5, 2026.
- NBIC report forms. The National Board of Boiler and Pressure Vessel Inspectors, November 6, 2026.
What this page is not
A guide written by Ahrom Labs, not engineering advice, and not yet reviewed by an Authorized Inspector. The ASME Code is copyrighted and sold by ASME: paragraphs are cited by number and explained in our own words, never reproduced. Check every figure against your copy of the 2025 Edition and with your Authorized Inspector before relying on it. Last updated .
Talk to us about your systems.
Tell us what's held together with workarounds right now. We reply to every message ourselves.