The ASME S stamp: power boiler certification
The S stamp is ASME's Section I Certificate of Authorization for power boilers: steam boilers above 15 psi and high-temperature water boilers, with their parts and piping. A shop needs a written quality control system, the Section I code books, an inspection agreement with an Authorized Inspection Agency and a joint review. The certificate is valid for three years and costs $4,500 plus an $11,000 advance deposit. An S holder can add the A and PP certificates without another full review.
Pujan Motiwala · Written to the ASME BPVC 2025 Edition · checked against ASME's and the National Board's public pages on

Video chapters (10)
- 0:00ASME Section I S Stamp Overview (Scope, Fees & 3-Year Renewal)
- 0:22Which Boilers Need S (Above 15 psi Steam / 160 psi or 250 °F Water)
- 0:42Section I Stamp Family: S, A, E, M, PP & PRT Parts Makers
- 1:015 Prerequisites: AIA, QC Manual, Code Books (B31.1) & Demo Item
- 1:23S Stamp Fees ($4,500 + $11K) & Adding A or PP Without a 2nd Review
- 1:46Section I Data Reports: P-2, P-3, P-3A, P-4 & P-4A + NB Filing
- 2:07Verbatim ASME Certification List, BPV-GUI-03, FAQ & Price Guide Quotes
- 2:25Boiler Data Books, Heat Traceability & Ember AI in US Boiler Demo
- 2:442025 Edition & Authorized Inspector Verification Notice
- 3:00Next Steps: QC Manual, Section I vs. IV & PP Piping Stamp (S19)
What is the ASME S stamp?
S is ASME's Certificate of Authorization for power boilers under Section I of the Boiler and Pressure Vessel Code. ASME lists it first among the Section I certificates, as "S - Power Boilers", followed by A (assembly), E (electric boilers), M (miniature boilers) and PP (pressure piping). A shop that holds S may build power boilers, their parts and their boiler external piping, and apply the ASME Certification Mark with the S designator.
As with every ASME stamp, the separate code symbol stamps were replaced in 2013 by one Certification Mark; "S stamp" is the name everyone still uses. See ASME stamps for the full list.
Which boilers need the S stamp?
Section I covers power boilers: steam boilers that generate steam above 15 psi, high-temperature water boilers above 160 psi or above 250 °F, and the economizers, superheaters, reheaters and external piping that are part of them. Typical work: watertube and firetube steam boilers for plants, heat recovery steam generators, waste heat boilers, superheaters and economizers, and the pressure parts of process steam generators.
Low-pressure heating boilers (steam up to 15 psi, hot water up to 160 psi and 250 °F) are built to Section IV with the H stamp instead. See Section I vs Section IV.
What is the difference between the S, A, E, M and PP stamps?
| Certificate | Scope |
|---|---|
| S | Power boilers: design and manufacture, parts and piping |
| A | Field assembly of power boilers from parts made by others |
| E | Electric boilers |
| M | Miniature boilers (small size and pressure limits in Section I) |
| PP | Pressure piping for power boilers, mainly boiler external piping |
A boiler maker usually holds S, often with PP. An erection contractor that assembles boilers on site holds A. A shop that only fabricates parts for others (headers, drums, tube panels) without design responsibility may hold the PRT parts certificate instead.
What does a shop need to get the S stamp?
- An inspection agreement. ASME's handbook: "the Applicant must have an inspection agreement in place with an ASME Accredited Authorized Inspection Agency (AIA)". Its table lists the S certificate as valid for 3 years with the agreement required. See Authorized Inspector.
- A quality control manual for Section I work: design and calculations, drawings, material control by heat number, welding, examination, heat treatment, hydrostatic test, calibration, nonconformances and records. See the QC manual.
- The code books. ASME lists S together with PP ("Pressure Piping and Power Boilers"): Section I, Section II Parts A, B, C and D, Section V, Section IX, B31.1 and CA-1.
- Welding qualifications to Section IX: procedures, welders and their continuity.
- A demonstration item for the joint review, built and inspected under the new system.
How much does the S stamp cost?
ASME's price guide: "All other Certificates: $4,500.00 per certificate and Advance Deposit: $11,000.00", plus $400 per Certification Mark stamp. The deposit goes toward the review. The inspection agency's contract, the code books and the work of writing the manual and qualifying procedures come on top. The certificate is renewed every three years.
Can an S holder add A and PP without another review?
Yes. ASME's FAQ: "A full ASME Joint Review is not required for: A holder of an ASME S Certificate who applies for an additional A or PP Certificate(s) of Authorization." ASME asks the last review's team leader and the shop's inspection agency to confirm in writing that the manual covers the added scope. A shop with only the U certificate needs a full review to add S.
Which data reports go with S work?
ASME's Section I forms include:
| Form | Use |
|---|---|
| P-2 | "Manufacturers' Data Report for All Types of Boilers Except Watertube and Electric" |
| P-3 | "Manufacturers' Data Report for Watertube Boilers, Superheaters, Waterwalls, and Economizers" |
| P-3A | "Engineering-Contractor Data Report for a Complete Boilers Unit" |
| P-4 | "Manufacturers' Partial Data Report", for parts made by one holder and used by another |
| P-4A | Fabricated piping (see the PP stamp) |
The shop completes the report, the Authorized Inspector signs it, and in most states it is registered with the National Board. See data reports and National Board registration.
What records does an S shop keep per boiler?
The calculations and drawings with revisions, material by heat number with its MTRs, a weld map with the procedure and welder per seam, NDE and PWHT records, the hydrostatic test, the ITP with its hold points signed, any NCRs, partial data reports from suppliers, and the signed data report. Together they make the manufacturer's data book.
Our US boiler demo keeps this chain per job: material by heat number, welds by procedure and welder, hold points, NCRs and the data book, with Ember AI answering questions about any job. See ERP for boiler and pressure vessel shops.
Quoted from the official text (11)
“S - Power Boilers”
ASME, Boiler and Pressure Vessel Certification page, Power Boilers list
“A - Assembly of Power Boilers”
ASME, Boiler and Pressure Vessel Certification page, Power Boilers list
“S- Power Boiler 3 Yes”
ASME BPV-GUI-03, Exhibit A (certificate, years valid, AIA agreement required)
“the Applicant must have an inspection agreement in place with an ASME Accredited Authorized Inspection Agency (AIA)”
ASME BPV-GUI-03, application requirements
“A full ASME Joint Review is not required for: A holder of an ASME S Certificate who applies for an additional A or PP Certificate(s) of Authorization.”
ASME Certification FAQ
“Pressure Piping and Power Boilers”
ASME, Required Code Books page, PP & S Certification
“All other Certificates: $4,500.00 per certificate and Advance Deposit: $11,000.00”
ASME, Price Guide for Certifications
“Manufacturers' Data Report for All Types of Boilers Except Watertube and Electric”
ASME, Data Report Forms page, Section I forms
“Manufacturers' Data Report for Watertube Boilers, Superheaters, Waterwalls, and Economizers”
ASME, Data Report Forms page, Section I forms
“Engineering-Contractor Data Report for a Complete Boilers Unit”
ASME, Data Report Forms page, Section I forms
“Manufacturers' Partial Data Report”
ASME, Data Report Forms page, Section I forms
WPS and PQR registers, welder continuity, heat numbers from receipt to nameplate, and the data report package: the records a Code shop keeps, in one system.
A boiler manufacturer's system, from enquiry to dispatch and the IBR folder, with sample logins: try the live demo.
A boiler and pressure vessel shop's system, from inquiry to shipping and the ASME data report package, with sample logins: try the live demo. Fixed price, scope agreed before work starts: see the prices.
Official sources
- Boiler and Pressure Vessel Certification. ASME, November 1, 2026.
- Boiler and Pressure Vessel Certificates of Authorization and the Certification Mark: Informational Handbook (BPV-GUI-03). ASME, May 12, 2023.
- Frequently Asked Questions (Certification and Accreditation). ASME, November 5, 2026.
- Required Code Books. ASME, November 5, 2026.
- Price Guide for Certifications. ASME, November 5, 2026.
- ASME Data Report Forms. ASME, November 5, 2026.
What this page is not
A guide written by Ahrom Labs, not engineering advice, and not yet reviewed by an Authorized Inspector. The ASME Code is copyrighted and sold by ASME: paragraphs are cited by number and explained in our own words, never reproduced. Check every figure against your copy of the 2025 Edition and with your Authorized Inspector before relying on it. Last updated .