How to get the ASME U stamp: steps, cost and timeline
To get the U stamp a shop buys the Code books, signs an inspection agreement with an ASME-accredited Authorized Inspection Agency, writes a quality control manual, applies to ASME through CA Connect with the fees, and passes a joint review: an on-site audit of the manual and a demonstration on real work or a mock-up. ASME's fee is $4,500 per certificate; the certificate lasts three years.
Pujan Motiwala · Written to the ASME BPVC 2025 Edition · checked against ASME's and the National Board's public pages on

Video chapters (10)
- 0:00How to Earn the ASME U Stamp (Overview & $4,500 Fee)
- 0:22The 9-Step Pipeline: Required Books, AIA, QC Manual & CA Connect
- 0:42Choosing an AIA, Cross-Referencing the Manual & Demo Item Scope
- 1:01Full ASME Fee Schedule: $4,900 (NB States) vs. $15,900 (ASME Designees)
- 1:25Timeline (~4 Months), 7-Day CA Connect Acceptance & 6-Month Renewal
- 1:48What Your Shop Must Demonstrate (MTRs, QW-322, NCs & India Export Route)
- 2:07Verbatim BPV-GUI-03, ASME Price Guide & Certification FAQ Excerpts
- 2:25Audit Readiness Rule: Align Daily Shop Habits Before Paying Fees
- 2:442025 Edition & Live Price Guide Verification Notice
- 3:00Next Steps: QC Manual, Authorized Inspector & Section I S Stamp (S18)
What are the steps to get a U stamp?
A shop gets the U stamp by preparing its quality system, applying to ASME, and passing an on-site joint review; ASME then issues a Certificate of Authorization for Section VIII, Division 1 pressure vessels and the Certification Mark with the U designator. ASME's certification process and informational handbook set out the route. In the order a shop usually does it:
- Decide the scope. U for Division 1 vessels, shop only or field work too, and any limits. The scope drives everything else; see ASME stamps.
- Buy the Code books. ASME lists the books required per certificate (below). Copies and unauthorized reproductions aren't accepted.
- Sign an inspection agreement with an ASME-accredited Authorized Inspection Agency. The agency's Authorized Inspector joins the review and then inspects every stamped job.
- Write the quality control manual and train the people who will follow it. In English, covering every element the Code requires for the scope. See the quality control manual.
- Apply through ASME's CA Connect, return the signed ASME Accreditation/Certification Agreement, and pay the certificate fee, stamp fee and any deposit.
- ASME checks the file. It asks your agency to confirm the inspection agreement and checks the application is complete; only then does it schedule the joint review.
- Prepare the demonstration. Real Code work, a mock-up, or both, taken through your system from drawing to data report.
- The joint review. A team leader (the ASME Designee) and a representative of your inspection agency audit the manual and watch the demonstration, then report to ASME with a recommendation.
- Certificate and stamp issued once ASME accepts the report. Valid for three years.
Which Code books does a U certificate need?
ASME's required list for the U certificate is Section II Parts A, B, C and D (materials), Section V (nondestructive examination), Section VIII Division 1, Section IX (welding, brazing and fusing qualifications) and CA-1, ASME's conformity assessment requirements. Section II Part C, Section V and Section IX can be left out only if welding, brazing and fusing aren't in the shop's scope. Electronic editions bought from a licensed reseller are accepted; a new edition becomes mandatory six months after it is published. See BPVC sections and Code editions.
Why do you need an Authorized Inspection Agency first?
ASME won't schedule the joint review until an accredited Authorized Inspection Agency confirms it has an inspection agreement with the shop. The handbook's table of certificates marks the U certificate as requiring an agency agreement. The agency is an organization accredited by ASME; its Authorized Inspector sits on the review team, then inspects and signs off each stamped vessel, so the agreement covers the review and every job after it. ASME publishes the list of accredited agencies, and its FAQ notes most work worldwide.
When comparing agencies, ask for the review fee, the hourly or per-visit rate for job inspections, travel charges, and how often the Inspector will be in the shop at your volume.
What goes in the quality control manual?
The manual is the shop's written description of how it meets each Code requirement in its scope: organization and authority, drawings and design calculations, material receipt and control, welding, NDE, heat treatment, calibration, examination and inspection, nonconformities, records and the Inspector's access. ASME's review teams use a "General" checklist for the U certificate, and the shop must complete it, cross-referencing each element to the paragraph of its manual that addresses it. The manual doesn't have to follow the checklist's order, but every element must be findable. See the quality control manual.
What is the demonstration item?
The demonstration item is the work the shop puts through its quality system during the joint review to show the manual is really used. ASME's FAQ says the demonstration must cover the administrative functions and the manufacturing, fabrication and testing of the product, and that every element of the system must be demonstrated; fabrication can be shown on current work, a mock-up built to current Code rules, or both. ASME gives no required size or number of items.
Most shops choose a small vessel they can take all the way through: design calculations, material receipt with MTRs, WPS and PQR, welder qualifications, NDE, a hydrostatic test and a completed data report. Any Code work in the shop during the review can be examined too.
Who leads the joint review?
The ASME Designee who leads the review is appointed by ASME, by the jurisdiction, or by the National Board, depending on where the shop is. The handbook says the jurisdiction appoints in Alaska, Delaware, Hawaii, Louisiana, Minnesota, Nebraska, Oklahoma, Texas and Washington; ASME appoints in Idaho, Wyoming, Puerto Rico, the Virgin Islands, all Canadian provinces, and wherever the jurisdiction is itself the inspection agency; the National Board appoints in the other US states. Who appoints changes what the shop pays for the review (below). See US and Canadian boiler laws.
How much does the ASME U stamp cost?
ASME's own fee is $4,500 per certificate plus $400 per Certification Mark stamp (plus tax and shipping), from its Price Guide on 5 November 2026. Where ASME appoints the Designee, ASME also takes an $11,000 advance review deposit that is applied to the cost of the review; the guide names reviews in Idaho, Wyoming, Puerto Rico and the Virgin Islands, and any review where the state or province is itself the inspection agency. The shop pays the Designee's travel and ASME's administrative fees from it, and the final invoice settles the difference either way. Where the National Board or a state appoints, it tells the shop its own review charges. ASME wants all fees and the deposit before it schedules the review. Prices are in US dollars and change; check the current guide.
| Item | Paid to | Amount |
|---|---|---|
| U certificate | ASME | $4,500 |
| Certification Mark (stamp), each | ASME | $400 plus tax and shipping |
| Advance review deposit, where ASME appoints the Designee | ASME | $11,000, applied to the review cost |
| Expedited joint review, if wanted | ASME | $2,750 |
| Manual or document review, if needed | ASME | $1,500 each |
| Joint review, where the National Board or a state appoints | National Board or the state | Set by them |
| Inspection agency: review attendance, then every job | The agency | Set by the agency |
| Code books | ASME or a licensed reseller | Per ASME's catalog |
| Manual writing, training, demonstration item, any consultant | Your own cost |
For example, a shop in Ohio (National Board appoints) pays ASME $4,900 for one certificate and one stamp, and the National Board and its inspection agency separately. A shop in Idaho (ASME appoints) pays ASME $15,900 before the review is scheduled, $4,500 plus $400 plus the $11,000 deposit, and the final invoice refunds what the review and travel don't use or bills any balance. Withdrawing after paying costs a $1,100 administrative fee, and cancelling dates already accepted costs $2,200 or more.
How long does it take to get a U stamp?
Plan on several months after the application, plus the time the shop needs to be ready. ASME's FAQ says reviews are generally scheduled about four months after it receives the completed application and fees; ASME emails proposed dates, which must be accepted in CA Connect within seven business days, and sends review details four to six weeks before. The certificate is issued after ASME approves the team leader's report.
The rest of the pace is set by the shop: writing a manual that matches how it really works, signing the agency agreement, and getting a demonstration item through every step. Apply when the manual is done and the demonstration job is planned, and book the review only when a full job can be shown end to end.
How do you renew a U stamp?
The certificate lasts three years, and renewal is another joint review. ASME sends a reminder ten months before expiry, and the renewal application, fees and any deposit must reach ASME at least six months before the expiry date, or the certificate may lapse. A shop with work in progress at expiry can ask for one six-month extension to finish the listed work: the request must reach ASME 30 days before expiry, with a $2,200 fee per certificate and a report from the inspection agency.
What should a shop's system keep for the review?
Whatever runs the shop, check that it can show the review team, for the demonstration job and every job after:
- The drawing and calculation revision used, and who approved it.
- Each material receipt with its MTR, heat number and the parts it went into; see MTRs.
- The WPS used on each weld, the welder's stamp and their qualification and continuity.
- NDE, heat treatment and test records, linked to the job.
- Nonconformities and how each was resolved, with the Inspector's acceptance.
- Hold points the Inspector signed, and the data report.
Can a shop in India get the U stamp?
Yes. The route is the same for a shop in India, and many Indian fabricators hold U and S certificates for export work. IBR 2026 lets an Indian Inspecting Authority inspect an export boiler to a foreign code; see buying ASME equipment from India and ASME vs IBR 2026.
Quoted from the official text (23)
“Certificates of Authorization to use the ASME Certification Mark are issued for 3-years”
ASME BPV-GUI-03, section 1
“ASME will move forward with scheduling the Joint Review.”
ASME BPV-GUI-03, section 2
“The Joint Review will consist of an on-site evaluation of the Applicant's QCS encompassing both a review of the Applicant's written description (QC Manual) and a demonstration of implementation of the program.”
ASME BPV-GUI-03, section 3
“they may be demonstrated using current work, a mock-up, or a combination of the two.”
ASME BPV-GUI-03, section 3
“The written description and documentation which support understanding of the program must be in English.”
ASME BPV-GUI-03, section 3
“The Applicant is required to indicate the corresponding cross references to the provisions in their written description (QC Manual) which address these elements.”
ASME BPV-GUI-03, section 3
“Certificate Holders are reminded by ASME ten months prior to the expiration date”
ASME BPV-GUI-03, section 2
“It is required that renewal applications, fees, and review deposit, as applicable, be received by ASME at least six months prior to the expiration date.”
ASME BPV-GUI-03, section 2
“Such a request for extension to complete work in progress must be received, by ASME, thirty days prior to the current expiration date.”
ASME BPV-GUI-03, Exhibit B
“An extension, if granted, will be for six months, with no further extension.”
ASME BPV-GUI-03, Exhibit B
“All other Certificates: $4,500.00 per certificate and Advance Deposit: $11,000.00”
ASME Price Guide, BPV certifications
“Certification Mark: $400.00 per stamp plus applicable tax and shipping”
ASME Price Guide, BPV certifications
“Where ASME appoints an ASME designee to conduct the review, ASME requires an advance review deposit (which will be applied to the cost of the review)”
ASME Price Guide, BPV review deposit
“Reviews in states and territories where ASME conducts the review (Idaho, Wyoming, Puerto Rico, and the Virgin Islands).”
ASME Price Guide, BPV review deposit
“Expedited Joint Review (BPV Only): $2,750.00”
ASME Price Guide, common fees
“all applicant companies submit requested certificate(s) fees, stamp fees, postage fee and advance deposit prior to being scheduled.”
ASME Price Guide, general notes
“there is an administrative fee of $1,100.00, which will be deducted from the original remittance.”
ASME Price Guide, general notes
“Extension of Certificate Expiration (Work-In-Progress): $2,200.00 per certificate”
ASME Price Guide, common fees
“ASME reviews/surveys are generally scheduled four months after receipt of the completed application forms and fees.”
ASME certification FAQ, scheduling
“The proposed review/survey dates must be accepted on CA Connect within seven business days after you receive our email notification.”
ASME certification FAQ, scheduling
“the certificate(s) will be issued after the report submitted by the team leader has been approved.”
ASME certification FAQ, scheduling
“Fabrication functions may be demonstrated using current work, a mock-up produced to current code rules, or a combination of the two. All elements of the QC System must be demonstrated.”
ASME certification FAQ, demonstration
“Most AIAs operate worldwide.”
ASME certification FAQ, inspection agencies
WPS and PQR registers, welder continuity, heat numbers from receipt to nameplate, and the data report package: the records a Code shop keeps, in one system.
A boiler manufacturer's system, from enquiry to dispatch and the IBR folder, with sample logins: try the live demo.
A boiler and pressure vessel shop's system, from inquiry to shipping and the ASME data report package, with sample logins: try the live demo. Fixed price, scope agreed before work starts: see the prices.
Official sources
- Boiler and Pressure Vessel Certification. ASME, November 1, 2026.
- Boiler and Pressure Vessel Certificates of Authorization and the Certification Mark: Informational Handbook (BPV-GUI-03). ASME, May 12, 2023.
- ASME Certification Process. ASME, November 5, 2026.
- Price Guide for Certifications. ASME, November 5, 2026.
- Required Code Books. ASME, November 5, 2026.
- Frequently Asked Questions (Certification and Accreditation). ASME, November 5, 2026.
What this page is not
A guide written by Ahrom Labs, not engineering advice, and not yet reviewed by an Authorized Inspector. The ASME Code is copyrighted and sold by ASME: paragraphs are cited by number and explained in our own words, never reproduced. Check every figure against your copy of the 2025 Edition and with your Authorized Inspector before relying on it. Last updated .
Talk to us about your systems.
Tell us what's held together with workarounds right now. We reply to every message ourselves.