Change orders in construction: pricing, approval, billing

A change order is a written agreement changing a construction contract's work, price or time, signed by owner and contractor (AIA's form is G701); a construction change directive (G714) orders changed work before the price is agreed. Get every change in writing before doing it, price it with backup, and bill it only once approved, as its own line on the pay application. Federal jobs give 30 days to assert an adjustment.

Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

A drawing with a revision cloud marked in red pencil, a ruler and an eraser: a change to the work.

What is a change order in construction?

A change order is a written agreement between owner and contractor that changes the work, the contract price, the contract time, or all three. It is signed by both (and usually the architect), and once signed its amount is added to the contract sum. AIA's standard form is G701; many owners use their own form with the same content: what changes, the price, the days, and the signatures.

Most disputes on a job are about changes: extra work done on a verbal OK, priced after the fact, argued about at closeout. The fix is procedural: no change is real until it is written, priced and approved, and every one is tracked until it is billed.

What's the difference between a change order and a construction change directive?

A change order is agreed by both sides; a construction change directive orders the work to go ahead before the price or time is agreed. AIA describes its G714 directive as for use where the owner and contractor "have not agreed on proposed changes in the contract sum or contract time", and under AIA's general conditions the owner can issue one without the contractor's signature. You do the work, keep the cost records, and the price is settled later, by a change order once it's agreed.

Change order (G701)Change directive (G714)
Price and timeAgreedNot yet agreed
Contractor signsYesNo
Work startsAfter signingOn the directive
BilledOnce signed, as its own lineOnce agreed and turned into a change order (or as the contract says)

Do I have to do extra work without a signed change order?

It depends on the contract and the state, but in Texas you may refuse once unsigned work gets too big. Since 1 September 2023, a Texas contractor or sub may decline owner-directed additional work without a written, fully executed change order once that work, plus earlier unsigned owner-directed work, exceeds 10% of the original contract amount, and isn't liable for damages for declining (Property Code 28.0091). On a $400,000 contract the line is $40,000: with $36,000 of unsigned work already done, a new $6,000 directive takes it to $42,000, and the contractor may decline it.

On federal jobs, a written or oral order from the contracting officer that changes the work counts as a change order only if you give written notice saying you regard it as one.

Will I get paid for work done on a verbal OK?

Often not without a fight. A verbal approval is hard to prove at closeout, and contracts usually say changes must be in writing. Get the scope and price in writing before you start, even as an email, and keep dated photos, daily reports and costs for any work done before the paperwork caught up.

How do I price a change order?

Build it from quantities, labor hours at your rates, material quotes and equipment, then add overhead and profit as the contract allows, with the backup attached:

LineAmount
Labor: 40 hours × $65$2,600
Material (supplier quote attached)$3,400
Equipment rental$500
Subtotal$6,500
Overhead and profit, 15%$975
Change order$7,475, 3 days added

The figures are made up. Ask for the time as well as the money: a change that adds work but no days can leave you paying liquidated damages for a delay the owner caused.

How long do I have to claim a change?

As the contract says; on federal jobs under FAR 52.243-4, you must assert your right to an adjustment within 30 days of the change order or your notice. Costs incurred more than 20 days before your written notice aren't adjusted (except for defective specifications), and nothing can be claimed after final payment. Under that rule, notice given on 1 March 2026 covers costs from 9 February 2026 onward. Private contracts, such as AIA's general conditions, have their own deadlines: read the changes article before the job starts.

What about hidden or different site conditions?

Give written notice promptly, before you disturb them. On federal jobs FAR 52.236-2 requires notice "before the conditions are disturbed" of subsurface or latent conditions that differ materially from the contract, or unusual unknown ones; if they do differ, the contract is adjusted in writing. No request is allowed after final payment.

Can I bill a pending change order?

No: bill only approved changes, each as its own line on the schedule of values, so the pay application shows the original contract sum, net change by change orders and the revised sum. Pending changes are tracked, not billed, and they belong on the WIP schedule, because their costs are already in the job.

Amount
Original contract sum$400,000
CO 1, approved$12,000
CO 2, pending$8,500 (tracked, not billed)
CO 3, rejected$4,000 (kept for the record)
Revised contract sum$412,000

Can signing a lien waiver give up a pending change order?

It can. A waiver that releases all claims through a date may release the extra work you haven't been paid for yet; read what each lien waiver covers, and list pending changes as an exception where the form allows.

What should a contractor's system keep for change orders?

  • A change log per job: number, description, who asked, date of notice, status, price and days.
  • The backup for each price, linked to the job's cost codes, so actual cost can be compared later.
  • Approved changes added to the contract value and the schedule of values, once.
  • Pending exposure: the total of unapproved changes per job, reviewed weekly.

In the construction demo's US build, a change order is raised as its own estimate against the accepted contract estimate; once accepted, its lines join the schedule of values labeled CO 1, CO 2 and are billed apart on the pay application. On the sample tower job, change order 1 adds $6,504 to a $245,856 schedule of values. It doesn't yet keep a change log with notice dates and days, or change directives billed before a price is agreed; those are parts we'd build.

Quoted from the official texts (12)

“make changes in the work within the general scope of the contract, including changes-”

FAR 52.243-4(a)

“Any other written or oral order (which, as used in this paragraph (b), includes direction, instruction, interpretation, or determination) from the Contracting Officer that causes a change shall be treated as a change order under this clause; Provided, that the Contractor gives the Contracting Officer written notice stating-”

FAR 52.243-4(b)

“Except as provided in this clause, no order, statement, or conduct of the Contracting Officer shall be treated as a change under this clause or entitle the Contractor to an equitable adjustment.”

FAR 52.243-4(c)

“no adjustment for any change under paragraph (b) of this clause shall be made for any costs incurred more than 20 days before the Contractor gives written notice as required.”

FAR 52.243-4(d)

“The Contractor must assert its right to an adjustment under this clause within 30 days after”

FAR 52.243-4(e)

“No proposal by the Contractor for an equitable adjustment shall be allowed if asserted after final payment under this contract.”

FAR 52.243-4(f)

“The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of-”

FAR 52.236-2(a)

“No request by the Contractor for an equitable adjustment to the contract for differing site conditions shall be allowed if made after final payment under this contract.”

FAR 52.236-2(d)

“exceeds 10 percent of the contractor's or subcontractor's original contract amount.”

Texas Property Code 28.0091(a)(2)

“A contractor or subcontractor who elects not to proceed with additional work as provided by this section is not responsible for damages associated with the election not to proceed.”

Texas Property Code 28.0091(b)

“G714–2017 is a directive for changes in the Work for use where the owner and contractor have not agreed on proposed changes in the contract sum or contract time.”

AIA, Summary of G714–2017

“the owner can issue a construction change directive without the contractor’s signature.”

AIA, change orders vs construction change directives

Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.

Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.

Official sources

What this page is not

A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .

Talk to us about your systems.

Tell us what's held together with workarounds right now. We reply to every message ourselves.