Daily progress reports and site records for contractors
A daily progress report (DPR) records, for one site and one day, the work done against each BOQ item, the labour and machines on site, material used, weather, hindrances and photos, so progress, cost and delays can be proved later. On CPWD works the official site records are the site order book, the cement register and an online inspection register; hindrances go in the site order book. A DPR from the phone feeds all of them.
Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

What is a daily progress report (DPR)?
A daily progress report is the record of one site for one day: the work done against each BOQ item, the labour and machines on site, the material used, the weather, any hindrance, and photos. It is the contractor's own record, kept whether or not the client asks for it, because it's what later proves progress for a bill, cost for the margin, and the cause of a delay for an extension of time.
What should a daily progress report record?
Everything that happened on the site that day that someone may later have to prove:
- Work done, per BOQ item and location, in the item's unit.
- Labour, by trade, from that day's attendance, with absentees and the reason.
- Machines on site and the hours each ran.
- Material used from site stock, per item.
- Weather, issues and hindrances, with who caused them and since when.
- Instructions received from the client's engineer.
- Photos, dated, of the work done and of any problem.
Which site records does CPWD require?
On CPWD works the Works Manual names the site documents: the site order book, a physical inspection register where applicable, the cement register and the dismantle register, kept under its standard operating procedure SOP 5/14. For projects, the inspection register is online, through CPWD's project management system, for senior officers to record their observations from the start of work to completion.
What is the site order book, and why does it matter?
It's the book on site where the client's engineer writes instructions to the contractor. Under CPWD's general conditions, the contractor's technical representative notes down instructions conveyed by the Engineer-in-Charge in the site order book and signs it, and the Engineer-in-Charge's decision as recorded there is final and binding on the contractor. Anything the engineer orders on site should therefore be in the site order book and, on the contractor's side, in that day's DPR.
How are hindrances recorded on CPWD works?
In the site order book. The physical hindrance register was dropped for works whose tenders were uploaded on or after 19 February 2019; now, when a hindrance causing delay comes to the junior or assistant engineer's notice, he writes it in the site order book and reports it to the Engineer-in-Charge at once. A contractor should record the same hindrance in its DPR the same day, with the date it started and photos, because extensions of time are argued from these dates.
Who should approve a daily progress report?
The project manager, before it counts. A report filed by the site engineer and approved by the PM is a checked record: only approved work should move the site's progress, feed the next measurement and bill, or count toward the weekly report to the client. A report sent back with a note is corrected and filed again.
Why file the DPR from a phone?
Because the work is on site and the evidence is on site. A report written in the evening from memory misses quantities and photos; one filed on a phone from the site, with attendance marked there, carries the time, the place and the pictures. Officers also inspect works often to check quality and specifications, and a dated photo record answers their questions quickly.
How do daily reports become the weekly report and the bill?
By adding them up rather than rewriting them. The week's approved reports give work done per BOQ item, labour man-days by trade, material used, machine hours, issues and photos for the client's weekly progress report; the same approved work feeds the measurement book and the material check against BOQ norms in material consumption.
Is there a free DPR format in Excel?
Yes: the daily progress report format (Excel, free under CC BY 4.0; also as a blank Word file and PDF to print): work done against BOQ items, labour by trade and contractor, materials received and issued, and issues and instructions, one sheet per site per day. A phone app does the same with less typing; see below.
What does the construction demo do?
In the construction demo, the site engineer files one report per site per day from a phone: quantity done against each BOQ line, labour by trade filled from that day's attendance, material used from the site's own stock, machine hours, weather, issues and up to six photos, shrunk on the phone before upload. Attendance is marked per worker on site, and a mark made away from the site's map pin is flagged. The project manager approves the report or returns it with a note, and only approved work counts toward progress. The weekly report for the client is built from the week's approved reports as a PDF, with sections chosen per client, and an approved report is posted to the site's Telegram group where one is set up. Datum AI answers "which sites haven't sent today's report?". It doesn't keep the site order book or the cement register in CPWD's format, or record hindrances as their own entries for an extension of time claim; those are parts we'd build.
Quoted from the official texts (7)
“For Projects, inspection register has been made online on CPWD Website for recording observations by Senior Officers.”
CPWD Works Manual 2022, para 5.7(1)
“For maintaining and operating other site documents viz Site order book, physical inspection register (wherever applicable), cement register, dismantle register etc details are given in SOP 5/14 which may be referred.”
CPWD Works Manual 2022, para 5.7(2)
“The requirement of maintaining and operating physical Hindrance Register has been dispensed with for all works whose NIQ/NITs are uploaded on or after 19/2/2019.”
CPWD Works Manual 2022, para 5.15(1)
“Whenever any hindrance whether on the part of department or contractor causing delay in the works comes to the notice of JE/AE, he should at once write in the site order book and immediately make a report to the Engineer-in-Charge.”
CPWD Works Manual 2022, para 5.15(1)
“The works shall be inspected frequently by various officers concerned with the work to ensure that the work in general is being carried out according to quality, design, drawing, and specifications.”
CPWD Works Manual 2022, para 5.6.6
“shall also note down instructions conveyed by the Engineer-in-Charge or his designated representative(s) in the site order book and shall affix his/their signature in token of noting down the instructions”
GCC 2023, contractor's technical representative
“the decision of the Engineer-In-Charge as recorded in the site order book and measurement recorded checked/test checked in Measurement Books shall be final and binding on the contractor.”
GCC 2023, site order book
Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.
Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.
Official sources
- CPWD Works Manual 2022. Central Public Works Department, Government of India (copy published by NDMC), June 30, 2022.
- General Conditions of Contract 2023, Construction Works (with DG CPWD's office memorandum of 22.09.2023). Central Public Works Department, Government of India (copy published by IIT Kanpur), September 22, 2023.
What this page is not
A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .
Talk to us about your systems.
Tell us what's held together with workarounds right now. We reply to every message ourselves.