Mechanics lien deadlines and preliminary notices by state

It depends on the state and your place in the chain. In California a sub sends a preliminary notice within 20 days of starting and records a lien within 90 days of completion (30 days after a notice of completion); in Florida the notice to owner is due within 45 days and the lien within 90 days of last work; Texas counts to the 15th day of a later month; New York allows 8 months. On federal jobs you claim against the payment bond instead.

Pujan Motiwala · Written for contractors and subcontractors · Checked against the statutes and official manuals cited on

A desk calendar with several dates circled in navy, a pencil and a brass hourglass: the deadlines for lien notices and claims.

What is a mechanics lien?

A mechanics lien is a claim against the property itself for unpaid work or materials on it: if the bill isn't paid, the claimant can ask a court to have the property sold to pay it. Every state has its own lien statute, and each has deadlines. Miss one and the lien is lost, even if the money is owed. Many states also require some claimants to send a notice early in the job (a preliminary notice, notice to owner or notice of claim) to keep the right to a lien.

What is a preliminary notice, and who has to send one?

A preliminary notice tells the owner, and usually the general contractor and lender, that you're working on the project and may claim a lien if you aren't paid. Subcontractors and suppliers usually have to send it; a general contractor with a contract directly with the owner often doesn't. It isn't a lien and it isn't a lien waiver; it only keeps the right open.

What are the deadlines in California, Texas, Florida, New York, Washington, Arizona and Kentucky?

StatePreliminary noticeLien deadlineSuit to enforce
CaliforniaWithin 20 days of first furnishing work (Civil Code 8204)Direct contractor: after completing its contract, before the earlier of 90 days after completion of the project and 60 days after a notice of completion (8412). Others: before the earlier of 90 days after completion and 30 days after a notice of completion (8414)Within 90 days of recording the lien (8460)
TexasSubs and suppliers: notice of claim by the 15th day of the third month after the month the work or materials were provided (2nd month on residential projects) (Property Code 53.056)Lien affidavit by the 15th day of the fourth month after the month work was completed (third month on residential projects) (53.052)Within one year of the last day to file the affidavit (53.158)
FloridaNotice to owner before starting or within 45 days of starting, for those not in contract with the owner (Statutes 713.06)Within 90 days after final furnishing of labor, services or materials (713.08)As the statute sets
New YorkNot required by Lien Law 10Within 8 months after completion or final furnishing; 4 months for a single-family home; 90 days after retainage was due for a retainage lien (Lien Law 10)As the statute sets
WashingtonNotice of right to claim a lien for those not contracting with the owner; it protects only what was supplied from 60 days before it is given (10 days on a new single-family residence) (RCW 60.04.031)Record the claim of lien within 90 days after you stop furnishing (RCW 60.04.091)As the statute sets
ArizonaPreliminary twenty day notice within 20 days of first furnishing to the jobsite (ARS 33-992.01)Record within 120 days after completion, or within 60 days after a recorded notice of completion (ARS 33-993)As the statute sets
KentuckyThose not in contract with the owner: written notice of intent to hold the property liable within 75 days after last furnishing for claims under $1,000, 120 days for claims over $1,000; 75 days on an owner-occupied one- or two-family home (KRS 376.010(4) and (5))File the lien statement with the county clerk within 6 months after you stop furnishing, and mail a copy to the owner within 7 days of filing (KRS 376.080)Within 12 months of filing the statement (KRS 376.090)

These are the main deadlines only. Each statute has its own form, service rules and exceptions, so read the state's text, or ask a construction lawyer, before relying on a date.

How do you count a California lien deadline?

From completion, or from the owner's notice of completion if one is recorded, whichever gives the earlier date. A subcontractor on a project completed on 1 June 2026, where the owner records a notice of completion on 10 June, must record its lien by 10 July 2026: 30 days after the notice, which is earlier than 30 August, 90 days after completion. The general contractor has until 9 August, 60 days after the notice. Each then has 90 days after recording to sue.

What happens if a California preliminary notice is late?

You don't lose everything, but you lose the work before it. A late notice still protects work done within the 20 days before it was served and after. A sub that started on 2 March 2026 should have served notice by 22 March; serving on 1 April protects only work from 12 March onward.

How do you count a Texas lien deadline?

By months, not days: to the 15th day of a month after the month the work was done. A subcontractor on a commercial job that provided labor in March 2026 and wasn't paid must send its notice of claim by 15 June 2026 (the third month after March) and, if work ended that month, file its lien affidavit by 15 July 2026 (the fourth month). A suit to foreclose must follow by 15 July 2027.

How long do you have in Florida and New York?

Florida: 90 days after you last furnished labor, services or materials, with the notice to owner served within 45 days of starting. Work that started on 2 March and ended on 1 June 2026 needs notice by 16 April and the claim of lien recorded by 30 August 2026. New York: 8 months after completion or your last work, so work last done on 1 June 2026 can be liened until 1 February 2027 (1 October 2026 for a single-family home).

Can you put a lien on a federal project?

The remedy on a federal job is the prime contractor's payment bond, under the Miller Act, rather than a lien on the property. A sub or supplier with a contract directly with the prime can sue on the bond once it hasn't been paid in full 90 days after its last work. A second-tier sub or supplier, in contract with a sub but not the prime, must first give the prime written notice within 90 days of its last work. Any suit must be brought within one year of the last labor or material.

Can a lien be filed for unpaid retainage?

Yes, where the statute allows it, often on its own clock. In New York a lien for retainage can be filed within 90 days after the date the retainage was due to be released; in Texas a sub claiming a lien for retainage has its own affidavit deadline, counted from the month the original contract was completed, terminated or abandoned (Property Code 53.052(d)).

How should a contractor track lien deadlines?

From the dates the system already has: the day each job and each sub started, the last day each worked or delivered, completion, any notice of completion, and the state of the project. From them, every deadline can be worked out per job and per party:

  • Preliminary notices due and sent, per sub and supplier, with proof of service.
  • Lien deadlines per job, counted under that state's rule, with a reminder well before each.
  • Lien waivers received against each payment, so nobody is paid without one.
  • Retainage still held, with its release date and any lien deadline for it.

The construction demo's US build tracks lien waivers per pay application, ours and our subs' and suppliers', conditional or unconditional. It doesn't yet send preliminary notices or work out lien deadlines by state; those are parts we'd build.

Quoted from the official texts (25)

“A preliminary notice shall be given not later than 20 days after the claimant has first furnished work on the work of improvement.”

California Civil Code 8204(a)

“The claimant shall, however, be entitled to record a lien, give a stop payment notice, and assert a claim against a payment bond only for work performed within 20 days prior to the service of the preliminary notice, and at any time thereafter.”

California Civil Code 8204(a)

“A direct contractor may not enforce a lien unless the contractor records a claim of lien after the contractor completes the direct contract, and before the earlier of the following times:”

California Civil Code 8412

“Sixty days after the owner records a notice of completion or cessation.”

California Civil Code 8412(b)

“Thirty days after the owner records a notice of completion or cessation.”

California Civil Code 8414(b)

“The claimant shall commence an action to enforce a lien within 90 days after recordation of the claim of lien.”

California Civil Code 8460(a)

“not later than the 15th day of the fourth month after the month in which the original contractor's work was completed, terminated, or abandoned”

Texas Property Code 53.052(a)(1)

“a claimant other than an original contractor claiming the lien must file an affidavit with the county clerk not later than the 15th day of the fourth month after the later of:”

Texas Property Code 53.052(b)

“for projects other than residential construction projects, not later than the 15th day of the third month after the month during which:”

Texas Property Code 53.056(a-1)(1)

“suit must be brought to foreclose the lien not later than the first anniversary of the last day a claimant may file the lien affidavit under Section 53.052.”

Texas Property Code 53.158(a)

“The notice must be served before commencing, or not later than 45 days after commencing, to furnish his or her labor, services, or materials”

Florida Statutes 713.06(2)(a)

“The claim of lien may be recorded at any time during the progress of the work or thereafter but not later than 90 days after the final furnishing of the labor or services or materials by the lienor.”

Florida Statutes 713.08(5)

“within eight months after the completion of the contract, or the final performance of the work, or the final furnishing of the materials”

New York Lien Law 10(1)

“where the notice of lien is for retainage, the notice of lien may be filed within ninety days after the date the retainage was due to be released”

New York Lien Law 10(1)

“may bring a civil action on the payment bond on giving written notice to the contractor within 90 days from the date on”

40 U.S.C. 3133(b)(2)

“a notice of claim of lien not later than ninety days after the person has ceased to furnish labor, professional services, materials, or equipment”

Washington RCW 60.04.091

“only protects the right to claim a lien for professional services, materials, or equipment supplied after the date which is sixty days before”

Washington RCW 60.04.031

“within one hundred twenty days after completion of a building, structure or improvement”

Arizona ARS 33-993(A)

“if a notice of completion has been recorded, within sixty days after recordation of such notice”

Arizona ARS 33-993(A)

“within six (6) months after he ceases to labor or furnish materials, files in the office of the county clerk”

Kentucky KRS 376.080(1)

“The claimant shall send by regular mail a copy of the statement to the property owner at his last known address within seven (7) days of filing the statement with the county clerk.”

Kentucky KRS 376.080(1)

“within seventy-five (75) days on claims amounting to less than one thousand dollars ($1,000) and one hundred twenty (120) days on claims in excess of one thousand dollars ($1,000) after the last item of material or labor is furnished”

Kentucky KRS 376.010(4)(a)

“unless an action is brought to enforce the lien within twelve (12) months from the day of filing the statement”

Kentucky KRS 376.090(1)

“shall be given not later than twenty days after the claimant has first furnished labor, professional services, materials, machinery, fixtures or tools to the jobsite”

Arizona ARS 33-992.01(C)

“An action brought under this subsection must be brought no later than one year after the day on which the last of the labor was performed or material was supplied by the person bringing the action.”

40 U.S.C. 3133(b)(4)

Bills, measurements, retention, change orders and job cost in one system, from site to accounts. Start with a working prototype of your main workflow, on your own data, credited to the build if you continue.

Daily reports, bills and stores for a sample contractor, with sample logins: try the construction demotry the construction demo. Its assistant, Datum AI, answers from the project records.

Official sources

What this page is not

A guide written by Ahrom Labs, a software company that builds operations systems for contractors. Laws, contract forms and manuals are explained from the texts cited, on the date shown; your contract and your state's or the department's current rules govern. Not legal, tax or accounting advice. AIA is a trademark of The American Institute of Architects; Ahrom Labs is not affiliated with it. Last updated .

Talk to us about your systems.

Tell us what's held together with workarounds right now. We reply to every message ourselves.