ASME Section XIII: relief valves and overpressure protection
Section XIII, first published in the 2021 Edition, holds the Code's rules for pressure relief devices: relief valves, rupture disks and pin devices, how their capacity is certified and how they are marked. The construction sections still say when a boiler or vessel needs protection and at what pressure; Section XIII says what the device must be. Device makers hold V, HV, UV, UD and related certificates.
Pujan Motiwala · Written to the ASME BPVC 2025 Edition · checked against ASME's and the National Board's public pages on

Video chapters (10)
- 0:00ASME Section XIII Overview: Relief Valves & Rupture Disks (2025)
- 0:16Why UG-125 Moved to UG-150 & One Section XIII Device Book
- 0:40Section XIII Designators: V, HV, UV, UD, UV3/UD3 & TV/TD
- 0:59How Valve Makers Certify: National Board Designee, No AIA & 90-Day Lab Rule
- 1:21Designer vs. Maker Duties: Set ≤ MAWP & 10% / 16% / 21% Rise Limits
- 1:43Protection by System Design, National Board VR Repair & T/O Testing
- 2:04Official ASME, BPV-GUI-03 & NBIC Citations
- 2:24Recording Valve Size, Set Pressure & Capacity on Boiler Data Reports
- 2:442025 Edition Notice & Authorized Inspector Verification
- 3:00Full Section XIII Guide, MAWP, National Board & Sheet S14 Next
What is ASME Section XIII?
Section XIII, Rules for Overpressure Protection, is the Code's section for pressure relief devices; ASME says it "sets requirements for design, materials, inspection, testing, and marking of pressure relief valves, rupture disks, and related devices". It was first published in the 2021 Edition, and the current one is 2025. The Code text is ASME's and paid; this guide cites paragraphs and your 2025 book is the authority.
Why did the relief valve rules move to Section XIII?
So that a device maker works to one book. Until 2021 each construction section carried its own relief device rules: Section VIII Division 1 in its UG-125 series, Sections I and IV in theirs. The 2021 Edition gathered the device rules into Section XIII, and the construction sections kept the requirement to protect the equipment, pointing to Section XIII for the device. Older drawings and data sheets still say "UG-125"; on new Division 1 work the vessel side is in the UG-150 series and the device side in Section XIII.
Which certificates does Section XIII use?
| Designator | Device |
|---|---|
| V | Boiler pressure relief valves |
| HV | Heating boiler safety valves |
| UV | Pressure vessel pressure relief valves |
| UD | Pressure vessel pressure relief devices (rupture disks and similar nonreclosing devices) |
| UV3, UD3 | High-pressure vessel (Division 3) valves and devices |
| TV, TD | Transport tank valves and devices |
The list is as ASME's certification page gives it. See ASME stamps for the full set.
How does a relief valve maker get certified?
Through a review led by the National Board, not an inspection agency. ASME's handbook says that for these certificates ASME "will notify the ASME Designated Organization, The National Board of Boiler and Pressure Vessel Inspectors, to appoint an ASME Designee to conduct the review", and no Authorized Inspection Agency agreement is needed. The device's relieving capacity must also be certified by test at an ASME-accepted laboratory: the tests must be scheduled within 90 days of the review and completed within six months, or the review is repeated.
What stays with the vessel or boiler designer?
The construction section still decides:
- that the vessel or boiler needs protection, and from what (a blocked outlet, a fire, a failed control);
- the set pressure, normally not above the MAWP;
- how far pressure may rise while the device relieves: in Division 1, generally 10% or 3 psi above MAWP for one device, 16% or 4 psi with several, and 21% for fire.
The designer sizes the device for the worst relieving case and specifies it; the device maker certifies its capacity and marks it.
Can a vessel be protected without a relief valve?
In defined cases. Division 1 allows overpressure protection by system design, where the vessel can't be overpressured by the system it sits in, under conditions the Code sets and the owner documents. It is the owner's responsibility and needs the jurisdiction's acceptance in many states; check your 2025 Division 1 and the jurisdiction before relying on it.
Who repairs relief valves in service?
Not a Section XIII certificate holder as such: repair and resetting of valves in service is done under the National Board's VR program to Part 4 of the National Board Inspection Code, which the National Board says is adopted into law by most US and Canadian jurisdictions. In-service testing has its own T/O program. See National Board registration and the R stamp.
What does our software keep for relief devices?
Our US boiler demo records each boiler's safety valves (size, set pressure, capacity) on its data report layout in the ASME record package. It doesn't size or certify valves. See ERP for boiler and pressure vessel shops.
Quoted from the official text (6)
“BPVC Section XIII sets requirements for design, materials, inspection, testing, and marking of pressure relief valves, rupture disks, and related devices.”
ASME Section XIII product page, description
“UV - Pressure Vessel Pressure Relief Valves”
ASME certification page, Section XIII certificates
“UD - Pressure Vessel Pressure Relief Devices”
ASME certification page, Section XIII certificates
“ASME will notify the ASME Designated Organization, The National Board of Boiler and Pressure Vessel Inspectors, to appoint an ASME Designee to conduct the review.”
ASME BPV-GUI-03, section 2
“it is necessary that all required capacity certification tests be scheduled within ninety days from the date of the review. If the tests are not successfully completed within six months from the date of the review, a new review must be conducted.”
ASME BPV-GUI-03, section 2
“The NBIC is adopted into law by most US and Canadian jurisdictions.”
NBBI NBIC page
WPS and PQR registers, welder continuity, heat numbers from receipt to nameplate, and the data report package: the records a Code shop keeps, in one system.
A boiler manufacturer's system, from enquiry to dispatch and the IBR folder, with sample logins: try the live demo.
A boiler and pressure vessel shop's system, from inquiry to shipping and the ASME data report package, with sample logins: try the live demo. Fixed price, scope agreed before work starts: see the prices.
Official sources
- Boiler and Pressure Vessel Certification. ASME, November 1, 2026.
- BPVC Section XIII: Rules for Overpressure Protection (2025). ASME, July 1, 2025.
- Boiler and Pressure Vessel Certificates of Authorization and the Certification Mark: Informational Handbook (BPV-GUI-03). ASME, May 12, 2023.
- National Board Inspection Code (NBIC). The National Board of Boiler and Pressure Vessel Inspectors, November 6, 2026.
What this page is not
A guide written by Ahrom Labs, not engineering advice, and not yet reviewed by an Authorized Inspector. The ASME Code is copyrighted and sold by ASME: paragraphs are cited by number and explained in our own words, never reproduced. Check every figure against your copy of the 2025 Edition and with your Authorized Inspector before relying on it. Last updated .