IBR 2026 questions, answered
43 questions on the Indian Boiler Regulations, 2026: what each form is, who issues it and under which regulation, and the rules for registration, inspection and records. Each links to its page, quoted from the Gazette. Free to reuse as data under CC BY 4.0.
Pujan Motiwala · Checked against the Gazette on · IBR 2026, in force from 1 October 2026
Download the questions and answers as JSON. Free under CC BY 4.0: use them, credit Ahrom Labs.
IBR 2026 guides
- What changed from IBR 1950 to IBR 2026?
- The Indian Boiler Regulations, 2026 replaced the Indian Boiler Regulations, 1950 on 1 October 2026, under the Boilers Act, 2025. The folder's forms were renumbered — the maker's Form III is now Form IV Part A — certificates can be filed electronically with digital signatures, and manufacturers must keep boiler records for at least five years. Read the guide
- What does IBR 2026 require for an economiser?
- An economiser is a part of the feed pipe heated by flue gas, so it comes under the Boilers Act and IBR 2026 Chapter 11 (regulations 357 to 392). It must be built under an Inspecting Authority, and before or with the first application for registration the maker furnishes Form XVI (certificate of manufacture and test) and the Inspecting Authority Form XV (inspection under construction). Assembled sections are tested to at least 1.5 times the maximum allowable working pressure for ten minutes. Read the guide
- How long must boiler records be kept under IBR 2026?
- Regulation 308 of IBR 2026 sets three retention periods for a boiler's certificates and approved drawings: the Inspecting Authority keeps them at least 3 years after registration, the manufacturer at least 5 years, and the owner for the boiler's entire life, passing them to any new owner. Read the guide
- Which documents are needed to register a boiler under IBR 2026?
- Under regulation 8 of IBR 2026, a boiler's registration application goes to the Chief Inspector with four sets of documents: the Inspecting Authority's certificate (Form I Part B or C), the maker's certificate (Form IV Part A), drawings, and the material certificates (Form V Part A, with the Form V Part B extract). Read the guide
- How is a boiler certificate renewed under IBR 2026?
- To renew a boiler's certificate under IBR 2026, the owner applies with the fee, prepares the boiler for inspection (emptied, cleaned, doors and fittings opened, valves taken apart) and the Competent Person inspects it inside and out, with a hydraulic test at 1.25 times the design pressure where one is required. Power plant boilers and waste heat boilers in continuous process plants follow Appendix H and Appendix I, and apply with Form IX. Read the guide
- What are the rules for small industrial boilers under IBR 2026?
- Under IBR 2026 a small industrial boiler is a shell boiler up to 7 kg/cm² (g) holding more than 25 and up to 500 litres, or a coil, once-through or water tube boiler up to 12 kg/cm² (g) and 150 litres. Its certificate of manufacture and test is Form XXII, which was Form XVII under IBR 1950. Read the guide
- At which stages is a boiler inspected during manufacture under IBR 2026?
- Appendix A of IBR 2026 lists the stages at which the Inspecting Authority or its Competent Person must inspect a boiler during manufacture: material identification, forming and edge preparation, completed shell welding, NDE reports, openings and attachments, heat treatment records, weld test specimens, and the hydraulic test with final examination and stamping. The maker gives at least four working days' notice before each stage. Read the guide
- How are steam pipes approved under IBR 2026?
- Under IBR 2026, plans of steam pipes with their mountings and fittings go to the Inspecting Authority before construction and to the Chief Inspector at the boiler's registration (regulation 323). Pipes are inspected and hydraulically tested before use, which a Form IV Part B certificate can show; the Chief Inspector then approves the line's pressure and temperature, which can't be changed without written authority. Read the guide
Inspecting Authority certificates
- What is IBR Form I Part A (formerly Form II-A)?
- The Inspecting Authority's certificate of inspection during construction for a boiler made to a foreign code for export. Prescribed under regulation 4. Issued by: The Inspecting Authority that supervised construction of a boiler built in India to a foreign code for export. Read the guide
- What is IBR Form I Part B (formerly Form II(1))?
- The Inspecting Authority's certificate that a shop-assembled boiler was built under its supervision, inspected at each stage and hydrostatically tested. Prescribed under regulation 8(a). Issued by: The Inspecting Authority, signed by its Competent Person and the Inspecting Authority, with date and seal. Read the guide
- What is IBR Form I Part C (formerly Form II(2))?
- The Inspecting Authority's certificate for the parts of a site-assembled boiler made and inspected at the maker's works. Prescribed under regulation 8(a). Issued by: The Inspecting Authority, signed by its Competent Person and the Inspecting Authority. Read the guide
- What is IBR Form I Part D (formerly Form II-B)?
- Replaces Form I Part B or C for a boiler built with variations from the standard conditions that the Board or the Inspecting Authority permitted. Prescribed under regulation 8(a)(iv). Issued by: The Inspecting Authority. Read the guide
- What is IBR Form I Part E (formerly Form II-C)?
- The Inspecting Authority's certificate once a boiler is erected at site and passes its hydrostatic test there. Prescribed under regulation 8(a)(v). Issued by: The Inspecting Authority, signed by its Competent Person and the Inspecting Authority. Read the guide
- What is IBR Form VIII?
- The maker's final inspection report for boiler components, approved by the Competent Person; components are erected at site on its strength. New in 2026. Prescribed under regulation 293. Issued by: The maker of the boiler components, approved by the Competent Person. Read the guide
Certificates of manufacture and test
- What is IBR Form IV Part A (formerly Form III)?
- The boiler maker's own certificate describing the boiler, its parts, materials, construction, mountings and tests. Prescribed under regulation 8(b). Issued by: The maker of the boiler or its representative; the Inspecting Authority countersigns it. Read the guide
- What is IBR Form IV Part B (formerly Form III-A)?
- The certificate of manufacture and test for steam and feed pipes. Prescribed under regulation 10. Issued by: The pipe maker and the Inspecting Authority. Well-known pipe makers may issue it online with a digital signature. Read the guide
- What is IBR Form IV Part C (formerly Form III-B)?
- The certificate of manufacture and test for boiler tubes. Prescribed under regulation 11. Issued by: The tube maker and the Inspecting Authority. Well-known tube makers may issue it electronically with a digital signature. Read the guide
- What is IBR Form IV Part D (formerly Form III-C)?
- The certificate for boiler mountings and fittings such as valves. Prescribed under regulation 12. Issued by: The maker of the mounting or fitting and the Inspecting Authority. Valve chests from well-known foundries or forges recognised by the Central Boilers Board carry the material particulars from their own certificates. Read the guide
- What is IBR Form IV Part E (formerly Form III-F)?
- The certificate for castings used in a boiler. Prescribed under regulation 13 and 50 to 57. Issued by: The foundry and the Inspecting Authority. Castings from well-known foundries recognised by the Central Boilers Board need no Inspecting Authority signature. Read the guide
- What is IBR Form IV Part F (formerly Form III-G)?
- The certificate for forgings used in a boiler. Prescribed under regulation 14 and 58 to 62. Issued by: The forge and the Inspecting Authority. Forgings from well-known forges recognised by the Central Boilers Board need no Inspecting Authority signature. Read the guide
- What is IBR Form IV Part G (formerly Form III-H)?
- The certificate for headers and similar standalone pressure parts, such as a steam header. Prescribed under regulation 15. Issued by: The maker of the part and the Inspecting Authority. Read the guide
- What is IBR Form IV Part H (formerly Form III-I)?
- The certificate for dished ends and end covers. Prescribed under regulation 16. Issued by: The maker of the dished end or end cover and the Inspecting Authority. Read the guide
- What is IBR Form XXII (formerly Form XVII)?
- The certificate of manufacture and test for a small industrial boiler. Prescribed under regulation 555(2). Issued by: Signed by the manufacturer, with the Competent Person and the Inspecting Authority certifying that the boiler was built under their supervision and inspected at stages. Read the guide
- What is IBR Form XXIII (formerly Form XVII)?
- The certificate of manufacture and test for a small solar boiler. Split out of the old Form XVII in 2026. Prescribed under regulation 596(3). Issued by: The manufacturer, with the Competent Person and the Inspecting Authority. Read the guide
Material certificates
- What is IBR Form V Part A (formerly Form IV)?
- The steel maker's certificate for plates and bars: charge numbers, chemical analysis and mechanical test results. Prescribed under regulation 8(d). Issued by: The steel maker. A Well-known steel maker recognised by the Central Boilers Board can issue it in place of an Inspecting Authority certificate. Read the guide
- What is IBR Form V Part B (formerly Form IV-A)?
- The extract that lists every material test certificate used in a boiler and its components, filed with the maker's Form IV Part A. Prescribed under regulation 8(d). Issued by: The boiler maker and its representative, from the original material test certificates, with the Competent Person and the Inspecting Authority also signing. Read the guide
Registration and use
- What is IBR Form X (formerly Form V)?
- The order that lets a newly inspected boiler be used before its registration and certificate are complete. Prescribed under regulation 300(2). Issued by: The Inspector, after inspecting the boiler and conducting the hydraulic test. Read the guide
- What is IBR Form XI (formerly Form I)?
- The boiler's lifelong inspection record: its particulars, dimensions, hydraulic and steam tests, inspections, repairs and accidents. Prescribed under regulation 306. Issued by: Prepared by the Inspector at registration; later entries by the Competent Person; kept in the Chief Inspector's office. Read the guide
- What is IBR Form XII (formerly Form VI)?
- The certificate that authorises a registered boiler's use, at the design pressure it states. Prescribed under regulation 310. Issued by: Granted under regulation 310 once the boiler is registered. Read the guide
- What is IBR Form XIV (formerly Form XIV)?
- The inspection record of a steam pipeline and its fittings: particulars, dimensions, calculations, hydraulic tests and inspection notes. Prescribed under regulation 322(3). Issued by: Prepared by the Inspector; later entries by the Competent Person at each inspection. Read the guide
Economisers
- What is IBR Form XV (formerly Form VII)?
- The Inspecting Authority's construction certificate for an economiser. Prescribed under regulation 358(3). Issued by: The Inspecting Authority that supervised the economiser's construction. Read the guide
- What is IBR Form XVI (formerly Form VIII)?
- The economiser maker's certificate of manufacture and test. Prescribed under regulation 358(4). Issued by: The economiser's constructor (maker). Read the guide
- What is IBR Form XVII (formerly Form X)?
- The provisional order for an economiser. Not the small industrial boiler certificate, which was Form XVII under IBR 1950 and is now Form XXII. Prescribed under regulation 381(5). Issued by: The Inspector, after inspecting an economiser for registration. Read the guide
- What is IBR Form XVIII (formerly Form IX)?
- The economiser's inspection and registration book. Prescribed under regulation 385. Issued by: The boilers inspection department of the State. Read the guide
- What is IBR Form XIX (formerly Form XI)?
- The certificate that authorises an economiser's use. Prescribed under regulation 387. Issued by: The Competent Person or Chief Inspector, under the Boilers Act, 2025. Read the guide
Welders
- What is IBR Form II (formerly Form XIII)?
- The certificate a welder must hold to weld boilers, boiler components, economisers, feed pipes, steam pipes and superheaters (regulation 7(1)(b)(iii)). Prescribed under regulation 7(1)(b)(iii) and 541. Issued by: The Competent Authority, after the welder passes the qualification test under regulation 541. Read the guide
- What is IBR Form XX?
- The continuity form submitted with a qualified boiler welder's request to renew their certificate. New in 2026. Prescribed under regulation 517 and 527(3). Issued by: The welder's employer, approved by the Competent Authority. Read the guide
- What is IBR Form XXI (formerly Form XII)?
- The record of a welder's qualification or requalification test. Prescribed under regulation 540. Issued by: The Competent Authority that conducts the welder's qualification or requalification test. Read the guide
Recognition by the Central Boilers Board
- What is IBR Form III?
- The questionnaire a firm answers to be recognised as a manufacturer of boilers or boiler components. New in 2026; recognition lasts three years. Prescribed under regulation 7(1)(b)(v). Issued by: The firm applying for recognition as a boiler or boiler component manufacturer. Read the guide
- What is IBR Form VI (formerly Form XV-A to XV-G)?
- Questionnaires for firms seeking recognition as an Inspecting Authority, Competent Authority, well-known steel maker, foundry or forge, tube or pipe maker, material testing laboratory or remnant life assessment organisation. Prescribed under regulation 17(2). Issued by: A firm seeking recognition by the Central Boilers Board: Part A for an Inspecting Authority, the other parts for the other recognised categories. Read the guide
- What is IBR Form VII (formerly Form XVI-A to XVI-I)?
- The Central Boilers Board's certificates of approval for the bodies and makers recognised under Form VI. Prescribed under regulation 19. Issued by: The Central Boilers Board, signed by its Secretary. Read the guide
Repairs and in-service inspection
- What is IBR Form IX (formerly Form XIX)?
- The details furnished with an application to inspect a boiler used for electric power generation (Appendix H) or a waste heat boiler in a continuous process plant (Appendix I), twelve or thirty-six months after certification. Prescribed under regulation 295(7) and 295(8). Issued by: The boiler owner. Read the guide
- What is IBR Form XIII (formerly Form XVIII)?
- The questionnaire a firm sends to the state's Chief Inspector of Boilers to be recognised as a boiler repairer (regulation 316(2)). Prescribed under regulation 316(2). Issued by: The firm applying for recognition as a repairer of boilers, economisers, steam lines and feed water lines. Read the guide
See a boiler's IBR folder produced from its material certificates, with a sample company.
Built for a boiler manufacturer: ERP for boiler manufacturers · how the folder is produced · other rules an ERP must meet
Official sources
- Indian Boiler Regulations, 2026 (Gazette of India, Extraordinary, No. 596). Central Boilers Board, Department for Promotion of Industry and Internal Trade, October 1, 2026.
What this page is not
A guide written by Ahrom Labs from the Gazette text; not legal advice. The Gazette governs wherever this page differs from it, and a state's Chief Inspector of Boilers may set procedures of their own. Last updated .